Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
WSOC TELEVISION, LLC Doing Business As: WSOC TELEVISION, LLC |
Director of Engineering/Operations 1901 North Tryon Street CHARLOTTE, NC 28206 United States |
+1 (704) 335-4732 | ted.hand@coxinc.com | Limited Liability Company |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Ted Hand Director of Engineering Operations WSOC Television, LLC |
Ted Hand 1901 North Tryon Street Charlotte, NC 28206 United States |
+1 (704) 335-4732 | ted.hand@coxinc.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | Yes |
Briefly describe transition plan | WSOC will install main transmitter first while operating on the auxiliary transmitter/antenna, then install the auxiliary system. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Auxiliary (Backup) | |
Description of Use | backup to main | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | DHD60P2 | |
Year | 2009 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power Capacity | 15 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Auxiliary (Backup) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Manufacturer | ||
Model | ULXTE-30 | |
Transmitter Type | Solid State | |
Solid State Cooling | Liquid Cooled | |
Solid State Power capacity | 19.2 kW | |
Justification for New Transmitter | Current transmitter will not tune to channel 19 |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Power | N/A | |
Rigid Conduit and Wiring | Yes | |
Size | 2 inches | |
Length | 250.0 feet | |
Other Electrical Service | Yes | |
Description | Wiring for water pumps and mask filter blowers | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Type | N/A | |
Size | N/A | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Size | N/A | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Name | Description |
---|---|
Combiner |
Use to combine WSOC Aux with WAXN Aux. Shared with WAXN-TV |
Coax Switch |
Coaxial switch use to switch from main to aux |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | CD3200P2 Sigma | |
Year | 1999 | |
Type | Inductive Output Tube | |
IOT Power Type | Three | |
Power Capacity | 55 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Manufacturer | ||
Model | ULXTE-72 | |
Transmitter Type | Solid State | |
Solid State Cooling | Liquid Cooled | |
Solid State Power capacity | 47.2 kW | |
Justification for New Transmitter | Current transmitter is tuned for channel 34 and will not tuned to channel 19 |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | Yes | |
Power | 500 kVA | |
Rigid Conduit and Wiring | Yes | |
Size | 2 inches | |
Length | 250.0 feet | |
Other Electrical Service | Yes | |
Description | Wiring for water pumps and mask filter blowers | |
HVAC Service | Does the replacement transmitter require HVAC Service? | Yes |
Type | Cooling Only | |
Size | 15 tons | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | Yes |
Size | 320.0 square feet | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Name | Description |
---|---|
RF Hanging Supplies |
Equipment to hang new mask filters and wave guide |
Plumbing Supplies |
Plumbing supplies for liquid cooled transmitter |
RF Equipment |
RF elbows, hangers, flanges, hardware kits |
Distilled Water |
Distilled water for cooling system |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | No | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | Class | Full Power |
Mounting | Top Mount | |
Antenna position in stack | Bottom | |
Polarization | Horizontal | |
Type | Broadband Panel | |
Number of Stations Supported | 1 | |
Number of Panels | 48 | |
Design power capacity in use | 65.0 % | |
Lower Limit | 470.00 MHz | |
Upper Limit | 608.00 MHz | |
Other Antenna Type | N/A | |
ERP: | 1000.0 kW | |
Manufacturer | ||
Model | TQP-0412-1 | |
Year | 1999 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | No | |
Is antenna directional? | No | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Types | Class | Full Power |
Mounting | Top Mount | |
Antenna position in stack | Bottom | |
Polarization | Horizontal | |
Type | Broadband Panel | |
Number of Stations Supported | 1 | |
Number of Panels/Bays | 48 | |
Lower Limit | 470.00 MHz | |
Upper Limit | 608.00 MHz | |
Design power capacity in use | 100.0 % | |
Other Antenna Type | N/A | |
ERP: | 1000.0 kW | |
Manufacturer | ||
Model | TFU-31EBT/VP-R | |
Year | 2019 | |
Justification for New Antenna | Current antenna will not tune to channel 19. Current antenna will not support top mounted WAXN's antenna. |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | No |
Type | ||
Number of channels supported | N/A | |
Frequencies of channels supported | N/A | |
Frequency | N/A | |
Do you need a combiner output splitter/switcher for dual feed lines? | N/A | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | Yes |
Broadband or Single Channel? | Single Channel | |
Feed Line Size | 7 3/16 inches inches | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | No |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Purchase New |
Use | Auxiliary (Backup) | |
Description of Use | backup to main | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing transmission line shared with another station or stations? | Yes | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Rigid | |
Diameter | 6 1/8 inches | |
Other Diameter | N/A | |
Segment Length | 19 1/2 inches | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 585 feet per run |
Facility ID | Call Sign |
---|---|
12793 | WAXN-TV |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Auxiliary (Backup) |
Description of Use | backup to main | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Type | Rigid | |
Diameter | 6 1/8 inches | |
Other Diameter | N/A | |
Segment Length | 20 inches | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 585 feet per run | |
Justification for New Transmission Line | current line will not work at new channel 19 |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Rigid | |
Diameter | 7 3/16 inches | |
Other Diameter | N/A | |
Segment Length | 19 1/2 inches | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 1050 feet per run |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Type | Rigid | |
Diameter | 7 3/16 inches | |
Other Diameter | N/A | |
Segment Length | 20 inches | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 1050 feet per run | |
Justification for New Transmission Line | Current line is 19 1/2' and will not work for new channel 19 |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Move Equipment |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Leased | |
Is this tower consider Complex? | No | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | Yes | |
Others Types of Users | No | |
Is tower documented for structural analysis? | Yes | |
Is tower compliant with Rev G? | Yes | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1004745 | |
Coordinates (NAD83) | Latitude (NAD83) | 35° 15' 42.0" N- |
Longitude (NAD83) | 080° 43' 37.0" W- | |
Overall Structure Height | 1082.01 feet | |
Support Structure Height | 970.13 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 855.96 feet | |
Structure Type | TOWER - Free Standing or Guyed Structure | |
Tower Owner | IWG Towers Assets II, LLC | |
Date Constructed | 01/31/2000 |
Facility ID | Call Sign | Service |
---|---|---|
12793 | WAXN-TV | DTV |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | N/A |
Helicopter Services Required | Are helicopter services required? | No |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 25 | |
Explanation | Project Manager to coordinate crew and materials on site. Design interior RF design | |
Outside RF consulting Engineering Services | Perform engineering study for new channel assignment and antenna development | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | Yes | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | Yes | |
For Main Facility | No | |
Prepare request for Special Temporary Authority | No | |
Quantity | N/A | |
Do you have Distributed Transmission System engineering services? | N/A | |
Critical Facility | N/A | |
Terrain-Shielded Facility | N/A | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | Yes | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | Yes | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Quantity | N/A | |
NEPA Section 106 environmental review | No | |
Environmental Assessment | No | |
ASR Modification | No | |
FAA Consultation (including preparation of FAA Form 7460) | No | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Address transition timing and coordination issues w/ other stations and wireless providers | No | |
RF Field Engineering Services | Comprehensive coverage verification via field study | Yes |
RF exposure measurements | Yes | |
Additional Field Engineering Service | Yes | |
Number of Days | 2 | |
Justification | Combined Auxiliary antenna will have to be field tuned |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Facility Expenses | Name | N/A |
Other Distributed Transmission System Expenses Not listed | N/A | |
Name | N/A | |
Is Notification of a Medical Facility required as a result of DTV broadcasting? | Yes | |
Permit and Filing Costs | Local Zoning | No |
Non-zoning permits | No | |
BLM or NFS Coordination | No | |
FCC Construction Permit Minor Change | Yes | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | Yes | |
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? | Yes | |
Does this relocation require MVPD Notification of a Channel Change? | Yes |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $2,422,800.00 | $2,601,564.87 | N/A | $2,118,362.46 | N/A |
Total for all systems | $4,277,970.00 | $4,129,562.37 | N/A | $2,407,170.46 | N/A |
Primary Transmitter ULXTE-72 | $1,710,300.00 | $1,946,700.00 | $1,909,490.84 | ||
Distilled Water | $1,300.00 | $1,300.00 | N/A | N/A | N/A |
RF Equipment | $40,000.00 | $40,000.00 | Transmitter reject loads would not fit within the room and had to moved to another room needing additional transmission lines, elbows, hangers and flanges | $36,692.39 | N/A |
Plumbing Supplies | $3,200.00 | $3,200.00 | N/A | $2,803.03 | N/A |
RF Hanging Supplies | $6,500.00 | $6,500.00 | N/A | $1,475.88 | N/A |
15 Ton system | $55,800.00 | $14,000.00 | Cost to move a HVAC unit. Shared cost with WAXN-TV 12793 | $13,288.00 | N/A |
Other -- Building Addition Size: 320.0 | $20,600.00 | $20,600.00 | N/A | $14,188.11 | N/A |
UHF - Liquid Cooled Solid State Transmitter 35 - 50 kW | $1,473,000.00 | $1,800,000.00 | Extra submission in transmitter line account. When removed, this will go down | $1,781,793.53 | The sub total is more than the Estimated Cost because the payment for $497,967.16 has been requested twice. The last item (#5) needs to be deleted. Thank you Ted H. |
Transformer 3 phase/480v - 500 KVA | $48,400.00 | $6,100.00 | Cost lowered by $41,000. Some added back to Overall electrical cost | $6,100.00 | N/A |
2" Rigid Conduit and Wiring (Cost per foot) | $6,500.00 | $0.00 | Cost lowered here but added to overall electrical cost | N/A | N/A |
Other Electrical Service: Wiring for water pumps and mask filter blowers | $55,000.00 | $55,000.00 | Based on actual quote. Changed conduit estimate to $0. Reduced Transformer from $41,000 to $6100. Overall electrical cost are lower than first estimated. Changed from $51482 to $55000 due to change in mask filter setup. | $53,149.90 | N/A |
Auxiliary Transmitter ULXTE-30 | $712,500.00 | $654,864.87 | $208,871.62 | ||
Combiner | $7,300.00 | $7,300.00 | This is half the cost. Shared with WAXN-TV | N/A | N/A |
Other Electrical Service: Wiring for water pumps and mask filter blowers | $10,000.00 | $10,000.00 | N/A | N/A | N/A |
UHF - Liquid Cooled Solid State Transmitter 14.2 - 20 kW | $684,000.00 | $626,614.87 | N/A | $208,871.62 | N/A |
2" Rigid Conduit and Wiring (Cost per foot) | $6,500.00 | $6,250.00 | N/A | N/A | N/A |
Coax Switch | $4,700.00 | $4,700.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Distilled Water | Information not provided. |
RF Equipment | |
Plumbing Supplies | |
RF Hanging Supplies | |
15 Ton system | |
Other -- Building Addition Size: 320.0 | |
UHF - Liquid Cooled Solid State Transmitter 35 - 50 kW | |
Transformer 3 phase/480v - 500 KVA | |
2" Rigid Conduit and Wiring (Cost per foot) | Information not provided. |
Other Electrical Service: Wiring for water pumps and mask filter blowers | |
Combiner | Information not provided. |
Other Electrical Service: Wiring for water pumps and mask filter blowers | Information not provided. |
UHF - Liquid Cooled Solid State Transmitter 14.2 - 20 kW | |
2" Rigid Conduit and Wiring (Cost per foot) | Information not provided. |
Coax Switch | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $521,360.00 | $391,952.50 | N/A | $179,979.75 | N/A |
Total for all systems | $4,277,970.00 | $4,129,562.37 | N/A | $2,407,170.46 | N/A |
Primary Antenna TUP-04-12-1 (S) | $253,730.00 | $4,185.00 | $4,185.00 | ||
UHF - High Power Top Mount (200-1000 kW), One station antenna, horizontally polarized | $247,000.00 | N/A | N/A | N/A | N/A |
Sweep test of existing antenna | $6,730.00 | $4,185.00 | ***System Notice: Estimate adjusted and locked because line has been superseded.***Dummy enter per Jeff Newman 202-418-2046 | $4,185.00 | Actual is lower than estimated |
Primary Antenna TFU-31EBT/VP-R | $267,630.00 | $387,767.50 | $175,794.75 | ||
UHF - High Power Top Mount (200-1000 kW), One station antenna, horizontally polarized | $247,000.00 | $371,205.00 | Based on actual quote from Dielectric LLC | $167,042.25 | N/A |
Sweep test of existing antenna | $6,730.00 | $4,180.00 | N/A | $2,880.00 | N/A |
Elbow complex, single channel, at antenna input, per 7 3/16. feedline (if needed) | $13,900.00 | $12,382.50 | N/A | $5,872.50 | N/A |
Actual Information Description | File Name |
---|---|
UHF - High Power Top Mount (200-1000 kW), One station antenna, horizontally polarized | Information not provided. |
Sweep test of existing antenna | |
UHF - High Power Top Mount (200-1000 kW), One station antenna, horizontally polarized | |
Sweep test of existing antenna | |
Elbow complex, single channel, at antenna input, per 7 3/16. feedline (if needed) |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $422,670.00 | $402,120.00 | N/A | $90,435.15 | N/A |
Total for all systems | $4,277,970.00 | $4,129,562.37 | N/A | $2,407,170.46 | N/A |
Primary Transmission Line | $304,500.00 | $289,800.00 | $90,435.15 | ||
Rigid Transmission Line - copper, 7 3/16" | $304,500.00 | $289,800.00 | N/A | $90,435.15 | N/A |
Auxiliary Transmission Line | $118,170.00 | $112,320.00 | $0.00 | ||
Rigid Transmission Line - copper, 6 1/8" | $118,170.00 | $112,320.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Rigid Transmission Line - copper, 7 3/16" | |
Rigid Transmission Line - copper, 6 1/8" | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $210,500.00 | $200,000.00 | N/A | $0.00 | N/A |
Total for all systems | $4,277,970.00 | $4,129,562.37 | N/A | $2,407,170.46 | N/A |
Primary Tower TOWER | $210,500.00 | $200,000.00 | $0.00 | ||
Tall Tower (greater than 500') | $210,500.00 | $200,000.00 | This is half the cost. The other half is on WAXN-TV's form. | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $155,365.00 | $163,700.00 | N/A | $18,393.10 | N/A |
Total for all systems | $4,277,970.00 | $4,129,562.37 | N/A | $2,407,170.46 | N/A |
Outside Professional Services | $155,365.00 | $163,700.00 | $18,393.10 | ||
Additional Field Engineering Service, 2 Days | $17,500.00 | $17,500.00 | N/A | N/A | N/A |
RF Exposure Measurements | $21,050.00 | $20,000.00 | N/A | N/A | N/A |
Comprehensive coverage verification via field study, if needed | $84,200.00 | $80,000.00 | N/A | N/A | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $2,365.00 | $2,250.00 | N/A | N/A | N/A |
Attorney Fees - Aux Antenna, prepare and File Form 2100 Construction Permit or License Application | $4,210.00 | $4,000.00 | N/A | $3,056.70 | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $5,260.00 | $5,000.00 | N/A | $4,813.40 | N/A |
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, License to Cover Application | $1,580.00 | $1,500.00 | N/A | N/A | N/A |
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, Construction Permit Application | $2,105.00 | $2,000.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $3,155.00 | $3,000.00 | N/A | N/A | N/A |
Perform engineering study for new channel assignment and antenna development | $7,360.00 | $22,200.00 | Actual Engineering Cost. See attached. | $10,523.00 | Actual is less than Estimated. This invoice is for work with WSOC and WAXN. Requesting 50% for WSOC |
Project management of the transition | $3,950.00 | $3,750.00 | N/A | N/A | N/A |
Prepare and or review reimbursement form | $2,630.00 | $2,500.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Additional Field Engineering Service, 2 Days | Information not provided. |
RF Exposure Measurements | Information not provided. |
Comprehensive coverage verification via field study, if needed | Information not provided. |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | Information not provided. |
Attorney Fees - Aux Antenna, prepare and File Form 2100 Construction Permit or License Application | |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | |
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, License to Cover Application | Information not provided. |
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, Construction Permit Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Perform engineering study for new channel assignment and antenna development | |
Project management of the transition | Information not provided. |
Prepare and or review reimbursement form | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $27,695.00 | $27,095.00 | N/A | $0.00 | N/A |
Total for all systems | $4,277,970.00 | $4,129,562.37 | N/A | $2,407,170.46 | N/A |
Other Expenses | $27,695.00 | $27,095.00 | $0.00 | ||
MVPD Notification of Channel Change | $7,500.00 | $7,500.00 | N/A | N/A | N/A |
Develop and air announcement of upcoming channel change | $1,100.00 | $1,100.00 | N/A | N/A | N/A |
DTV Medical Facility Notification | $11,550.00 | $11,000.00 | N/A | N/A | N/A |
FCC Filing Fees - Form 2100 minor change CP application | $1,110.00 | $1,070.00 | N/A | N/A | N/A |
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $325.00 | N/A | N/A | N/A |
Disposal Costs (for equipment and other waste, net of any salvage value) | $3,500.00 | $3,500.00 | N/A | N/A | N/A |
Equipment Delivery and Handling Charges | $0.00 | $0.00 | N/A | $0.00 | N/A |
Equipment Storage | $2,600.00 | $2,600.00 | N/A | N/A | N/A |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $4,277,970.00 | $4,129,562.37 | $2,407,170.46 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | No |
Construction of final facilities or all necessary modifications are complete. | No |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Ted Hand Director of Engineering/Operations 10/06/2018 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Ted Hand Director of Engineering/Operations 10/06/2018 |