Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
AGAPE BROADCASTERS, INC. Doing Business As: AGAPE BROADCASTERS, INC. |
David Thompson P.O. BOX 1469 CROWLEY, LA 70527 United States |
+1 (337) 783-1560 | davidt@familyvisiontv.com | Corporation |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
The Preparer is same as the reimbursement contact. |
|
|
|
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | No |
Briefly describe transition plan | THIS AMENDMENT REFLECTS THE STATION DECISION TO INSTALL A SINGLE CHANNEL ANTENNA FOR CH 19 TO REDUCE COST BY $137,610.00 AND CONTROL TPO REQUIREMENT. EXISTING XMTR AND ANTENNA NOT RETUNABLE. STATION FEEDS CABLE HEAD ENDS OFF AIR. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | AT7800 | |
Year | 2009 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power Capacity | 1 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Manufacturer | ||
Model | TMU9 | |
Transmitter Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | 1.8 kW | |
Justification for New Transmitter | Current transmitter not supported by manufacturer for parts availability. |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Power | N/A | |
Rigid Conduit and Wiring | No | |
Size | N/A | |
Length | N/A | |
Other Electrical Service | No | |
Description | N/A | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Type | N/A | |
Size | N/A | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Size | N/A | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Name | Description |
---|---|
TBD-Transmitter |
FIVE DAYS INSTALLING AND TESTING TRANSMITTER. PROOF |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | No | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | Class | Class A |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels | N/A | |
Design power capacity in use | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Other Antenna Type | N/A | |
ERP: | 15.0 kW | |
Manufacturer | ||
Model | SHI2010-32 | |
Year | 2000 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | No | |
Is antenna directional? | No | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Types | Class | Class A |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Elliptical | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels/Bays | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Design power capacity in use | N/A | |
Other Antenna Type | N/A | |
ERP: | 15.0 kW | |
Manufacturer | ||
Model | PSILPD24OI-19-EP | |
Year | 2018 | |
Justification for New Antenna | OLD ANTENNA CAN NOT BE RETUNED. |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | No |
Type | ||
Number of channels supported | N/A | |
Frequencies of channels supported | N/A | |
Frequency | N/A | |
Do you need a combiner output splitter/switcher for dual feed lines? | N/A | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | Yes |
Broadband or Single Channel? | Single Channel | |
Feed Line Size | 3 1/8 inches inches | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | No |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | No |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Move Equipment |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Leased | |
Is this tower consider Complex? | No | |
Is this tower currently shared with any other stations? | No | |
One or more FM, AM or TV radio broadcaster(s) | N/A | |
Others Types of Users | N/A | |
Is tower documented for structural analysis? | Unknown | |
Is tower compliant with Rev G? | Unknown | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1020854 | |
Coordinates (NAD83) | Latitude (NAD83) | 30° 02' 55.0" N- |
Longitude (NAD83) | 091° 59' 49.0" W- | |
Overall Structure Height | 583.98 feet | |
Support Structure Height | 583.98 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 20.01 feet | |
Structure Type | TOWER - Free Standing or Guyed Structure | |
Tower Owner | CALS COMMUNICATIONS SERVICE INC | |
Date Constructed | 10/15/1992 |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | N/A |
Helicopter Services Required | Are helicopter services required? | No |
Name | Description |
---|---|
TOWER RIGGING |
EXPENSE TO REMOVE EXISTING SHIVELY 32 SLOT AND INSTALL NEW 24 SLOT |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 100 | |
Explanation | STATION HAS CONTRACT ENGINEER WHO WILL REQUIRE ADDITIONAL HOURS TO SUPERVISE CREW AND MANAGE ALL ASPECTS OF PROJECT INCLUDING COORDINATION WITH CABLE COMPANIES | |
Outside RF consulting Engineering Services | Perform engineering study for new channel assignment and antenna development | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Quantity | N/A | |
Do you have Distributed Transmission System engineering services? | N/A | |
Critical Facility | N/A | |
Terrain-Shielded Facility | N/A | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Quantity | N/A | |
NEPA Section 106 environmental review | No | |
Environmental Assessment | No | |
ASR Modification | No | |
FAA Consultation (including preparation of FAA Form 7460) | No | |
Negotiation of Lease and other Matter for Shared Locations | Yes | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Address transition timing and coordination issues w/ other stations and wireless providers | Yes | |
RF Field Engineering Services | Comprehensive coverage verification via field study | No |
RF exposure measurements | No | |
Additional Field Engineering Service | Yes | |
Number of Days | 5 | |
Justification | TRANSMITTER INSTALLATION, PROOF AND TESTING |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Facility Expenses | Name | N/A |
Other Distributed Transmission System Expenses Not listed | N/A | |
Name | N/A | |
Is Notification of a Medical Facility required as a result of DTV broadcasting? | Yes | |
Permit and Filing Costs | Local Zoning | No |
Non-zoning permits | Yes | |
BLM or NFS Coordination | No | |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | Yes | |
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? | Yes | |
Does this relocation require MVPD Notification of a Channel Change? | Yes |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $126,000.00 | $70,040.65 | N/A | $70,040.65 | N/A |
Total for all systems | $505,505.00 | $231,015.65 | N/A | $113,190.65 | N/A |
Primary Transmitter TMU9 | $126,000.00 | $70,040.65 | $70,040.65 | ||
TBD-Transmitter | $0.00 | $0.00 | N/A | N/A | N/A |
UHF - Air Cooled Solid State Transmitter 1 - 2.5 kW | $126,000.00 | $70,040.65 | SJ Ramer Associates Quote 1820R. Estimated cost increased to match actual invoices received. | $70,040.65 | N/A |
Actual Information Description | File Name |
---|---|
TBD-Transmitter | Information not provided. |
UHF - Air Cooled Solid State Transmitter 1 - 2.5 kW |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $40,630.00 | $43,650.00 | N/A | $37,650.00 | N/A |
Total for all systems | $505,505.00 | $231,015.65 | N/A | $113,190.65 | N/A |
Primary Antenna PSILPD24OI-19-EP | $40,630.00 | $43,650.00 | $37,650.00 | ||
UHF - Lower Power Side Mount, Class A One Station antenna -- basic | $26,300.00 | $34,650.00 | SEE ATTACHED QUOTE. THE EXISTING SHIVELY ANTENNA IS A 32 SLOT. THIS IS A REDUCTION TO A 24 SLOT ANTENNA | $34,650.00 | N/A |
Sweep test of existing antenna | $6,730.00 | $6,000.00 | N/A | N/A | N/A |
Elbow complex, single channel, at antenna input, per 3 1/8. feedline (if needed) | $7,600.00 | $3,000.00 | N/A | $3,000.00 | N/A |
Actual Information Description | File Name |
---|---|
UHF - Lower Power Side Mount, Class A One Station antenna -- basic | |
Sweep test of existing antenna | Information not provided. |
Elbow complex, single channel, at antenna input, per 3 1/8. feedline (if needed) |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $235,500.00 | $25,000.00 | N/A | $0.00 | N/A |
Total for all systems | $505,505.00 | $231,015.65 | N/A | $113,190.65 | N/A |
Primary Tower TOWER | $235,500.00 | $25,000.00 | $0.00 | ||
Tall Tower (greater than 500') | $210,500.00 | $0.00 | RIGGING | N/A | N/A |
TOWER RIGGING | $25,000.00 | $25,000.00 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $52,490.00 | $44,000.00 | N/A | $4,405.55 | N/A |
Total for all systems | $505,505.00 | $231,015.65 | N/A | $113,190.65 | N/A |
Outside Professional Services | $52,490.00 | $44,000.00 | $4,405.55 | ||
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $2,365.00 | $2,250.00 | N/A | N/A | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $5,260.00 | $5,000.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,580.00 | $1,500.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $3,155.00 | $1,750.00 | N/A | N/A | N/A |
Perform engineering study for new channel assignment and antenna development | $7,360.00 | $2,500.00 | N/A | N/A | N/A |
Address transition timing and coordination issues w/ other stations and wireless | $2,630.00 | $2,500.00 | N/A | N/A | N/A |
Prepare and or review reimbursement form | $2,630.00 | $2,000.00 | N/A | N/A | N/A |
Attorney Fees - Negotiation of lease and other matters for shared locations | $4,210.00 | $4,000.00 | N/A | N/A | N/A |
Additional Field Engineering Service, 5 Days | $7,500.00 | $7,500.00 | N/A | N/A | N/A |
Project management of the transition | $15,800.00 | $15,000.00 | N/A | $4,405.55 | N/A |
Actual Information Description | File Name |
---|---|
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | Information not provided. |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Perform engineering study for new channel assignment and antenna development | Information not provided. |
Address transition timing and coordination issues w/ other stations and wireless | Information not provided. |
Prepare and or review reimbursement form | Information not provided. |
Attorney Fees - Negotiation of lease and other matters for shared locations | Information not provided. |
Additional Field Engineering Service, 5 Days | Information not provided. |
Project management of the transition |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $50,885.00 | $48,325.00 | N/A | $1,094.45 | N/A |
Total for all systems | $505,505.00 | $231,015.65 | N/A | $113,190.65 | N/A |
Other Expenses | $50,885.00 | $48,325.00 | $1,094.45 | ||
MVPD Notification of Channel Change | $9,000.00 | $9,000.00 | N/A | N/A | N/A |
Develop and air announcement of upcoming channel change | $3,500.00 | $3,500.00 | N/A | N/A | N/A |
Equipment Storage | $3,500.00 | $3,500.00 | N/A | N/A | N/A |
Equipment Delivery and Handling Charges | $12,000.00 | $12,000.00 | N/A | $1,094.45 | N/A |
Disposal Costs (for equipment and other waste, net of any salvage value) | $7,500.00 | $7,500.00 | N/A | N/A | N/A |
DTV Medical Facility Notification | $11,550.00 | $9,000.00 | N/A | N/A | N/A |
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $325.00 | N/A | N/A | N/A |
Non-zoning permits | $3,500.00 | $3,500.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
MVPD Notification of Channel Change | Information not provided. |
Develop and air announcement of upcoming channel change | Information not provided. |
Equipment Storage | Information not provided. |
Equipment Delivery and Handling Charges | |
Disposal Costs (for equipment and other waste, net of any salvage value) | Information not provided. |
DTV Medical Facility Notification | Information not provided. |
FCC Filing Fees - Form 2100 license to cover application | Information not provided. |
Non-zoning permits | Information not provided. |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $505,505.00 | $231,015.65 | $113,190.65 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | No |
Construction of final facilities or all necessary modifications are complete. | No |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | David Thompson Station Manager 09/05/2018 |