Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
GRAHAM MEDIA GROUP, FLORIDA. INC. Doing Business As: GRAHAM MEDIA GROUP, FLORIDA. INC. |
James Lowery 4 BROADCAST PLACE JACKSONVILLE, FL 32207 United States |
+1 (904) 393-9871 | jlowery@wjxt.com | Corporation |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
William T Godfrey , Jr. . Consulting Engineers Kessler and Gehman Associates, Inc. |
William T. Godfrey, Jr. Kessler and Gehman Associates, Inc. 507-D NW 60th Street Gainesville, FL 32607 United States |
+1 (352) 332-3157 | bill@kesslerandgehman.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | Yes |
Briefly describe transition plan | Replace the transmitter, antenna and transmission line. Analyze and modify 222-F candelabra tower. Establish alternate-site interim facility. May share with WCWJ as well, but per staff instructions, cost estimates on this form assume standalone operation. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | Sigma CD3200P2 | |
Year | 2008 | |
Type | Inductive Output Tube | |
IOT Power Type | Two | |
Power Capacity | 42 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Manufacturer | ||
Model | THU9EVO-24 | |
Transmitter Type | Solid State | |
Solid State Cooling | Liquid Cooled | |
Solid State Power capacity | 37.0 kW | |
Justification for New Transmitter | ERP: 550 kW RMS Gain: 18.8 Az Pat Gain (H-pol): 1.38 Line Eff: 80.8% Mask Filter Eff: 93.1% Combiner Eff: 93.3% TPO Required: 30.2 kW One Step Up: 37.0 kW |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | Yes | |
Transformer (480V) | Yes | |
Power | 300 kVA | |
Rigid Conduit and Wiring | Yes | |
Size | 3 inches | |
Length | 100.0 feet | |
Other Electrical Service | Yes | |
Description | Additional electrical services required for constructing the new LCSS TX while the existing IOT transmitter is in operation. | |
HVAC Service | Does the replacement transmitter require HVAC Service? | Yes |
Type | Cooling Only | |
Size | 10 tons | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Size | N/A | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Name | Description |
---|---|
Standby Exciter and Switch |
Standby Exciter with Automatic Change Over Switch |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Interim |
Description of Use | N/A | |
Change Type | Purchase | |
Manufacturer | ||
Model | THU9EVO-30 | |
Transmitter Type | Solid State | |
Solid State Cooling | Liquid Cooled | |
Solid State Power capacity | 38.3 kW | |
Justification for New Transmitter | The WJXT tower does not have sufficient space for an interim antenna; therefore, the interim facility must be located at an alternate site requiring a new interim transmitter capable of maintaining existing coverage. |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | Yes |
Switchgear (industrial 800 amp) | Yes | |
Transformer (480V) | Yes | |
Power | 300 kVA | |
Rigid Conduit and Wiring | Yes | |
Size | 2 inches | |
Length | 300.0 feet | |
Other Electrical Service | Yes | |
Description | Additional services required to install new transmitter at alternate site (see attached quotes for monthly lease expenses; transmitter building costs; and electrical services costs). | |
HVAC Service | Does the replacement transmitter require HVAC Service? | Yes |
Type | Cooling Only | |
Size | 10 tons | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | Yes |
Size | 450.0 square feet | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A | |
Inside RF System | Is an additional interior RF system required to support this interim transmitter? | Yes |
Name | Description |
---|---|
8-Pole Mask Filter |
WJXT-D18 is located less than 2 km from WJAX-D19 (1st adjacent stations). |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | Yes | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | Yes | |
Existing Antenna Manufacturer and Type | Class | Full Power |
Mounting | Top Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels | N/A | |
Design power capacity in use | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Other Antenna Type | N/A | |
ERP: | 976.0 kW | |
Manufacturer | ||
Model | TFU-30GTH 06 | |
Year | 2008 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | Yes | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | Yes | |
New Antenna Manufacturer and Types | Class | Full Power |
Mounting | Top Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Elliptical | |
Type | Broadband Slot | |
Number of Stations Supported | 2 | |
Number of Panels/Bays | 24 | |
Lower Limit | 494.00 MHz | |
Upper Limit | 512.00 MHz | |
Design power capacity in use | 45.9 % | |
Other Antenna Type | N/A | |
ERP: | 550.0 kW | |
Manufacturer | ||
Model | TFU-24GTH/VP-R TC 06SP | |
Year | 2018 | |
Justification for New Antenna | The existing main antenna is a top-mount (candelabra) slot which cannot accommodate the post-auction channel. The proposed antenna is a broadband slot that will be shared with the WCWJ "unable to construct" post-auction facility. |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | Yes |
Type | New | |
Number of channels supported | 2 | |
Frequencies of channels supported | RF channel | |
Frequency | N/A | |
Do you need a combiner output splitter/switcher for dual feed lines? | No | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | Yes |
Broadband or Single Channel? | Broadband | |
Feed Line Size | 8 3/16 inches inches | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | No |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
RF Channel Number |
---|
18 |
20 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Interim |
Description of Use | N/A | |
Change Type | Purchase New | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | No | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | Yes | |
New Antenna Manufacturer and Type | Class | Full Power |
Mounting | Top Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels/Bays | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Design power capacity in use | N/A | |
Other Antenna Type | N/A | |
ERP: | 976.0 kW | |
Manufacturer | ||
Model | TFU-24WB C160 | |
Year | 2018 | |
Justification for New Antenna | An interim antenna is necessary to keep station on the air during primary antenna replacement and for the duration of the assigned phase. The interim facility will be located at an alternate site. |
Section | Question | Response |
---|---|---|
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | Yes |
Broadband or Single Channel? | S | |
Feed Line Size | 7 3/16 inches | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for an antenna? | No |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Interim |
Description of Use | N/A | |
Change Type | Purchase New | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | Yes | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | Yes | |
New Antenna Manufacturer and Type | Class | Full Power |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Broadband Slot | |
Number of Stations Supported | 2 | |
Number of Panels/Bays | 8 | |
Lower Limit | 192.00 MHz | |
Upper Limit | 216.00 MHz | |
Design power capacity in use | 100.0 % | |
Other Antenna Type | N/A | |
ERP: | 82.8 kW | |
Manufacturer | ||
Model | TLSV-8BB | |
Year | 2018 | |
Justification for New Antenna | The WTLV and WJXX VHF stations share an antenna on the candelabra and require an interim antenna during the WJXT/WCWJ repack in order to remain on the air as required in the lease agreement. The ERP above combines ERPs for WTLV/WJXX since shared. |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | Yes |
Type | New | |
Number of channels supported | 2 | |
Frequencies of channels supported | RF channel | |
Frequency | N/A | |
Do you need a combiner output splitter/switcher for dual feed lines? | No | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | Yes |
Broadband or Single Channel? | B | |
Feed Line Size | 4 1/16 inches | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for an antenna? | Yes |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | Yes |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
RF Channel Number |
---|
10 |
13 |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Rigid | |
Diameter | 6 1/8 inches | |
Other Diameter | N/A | |
Segment Length | 19 1/2 inches | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 1155 feet per run |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Type | Rigid | |
Diameter | 8 3/16 inches | |
Other Diameter | N/A | |
Segment Length | 20 inches | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 1155 feet per run | |
Justification for New Transmission Line | The power rating for the existing primary 6-1/8" transmission line is not capable of handling the power required for WJXT and WCWJ shared operation. |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Interim |
Description of Use | N/A | |
Change Type | Purchase New | |
Type | Rigid | |
Diameter | 7 3/16 inches | |
Segment Length | 20' | |
Other Segment Length | ||
Number of parallel runs | 1 | |
Length | 1075 feet per run | |
Justification for New Transmission Line | An interim transmission line is necessary to keep the pre-auction station on the air during the primary antenna replacement and for the duration of the assigned phase. The Interim facility must be at an alternate site since the WJXT tower is fully loaded. |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Auxiliary (Backup) | |
Description of Use | Interim Tower | |
Ownership | Leased | |
Is this tower consider Complex? | No | |
Is this tower currently shared with any other stations? | No | |
One or more FM, AM or TV radio broadcaster(s) | N/A | |
Others Types of Users | N/A | |
Is tower documented for structural analysis? | Yes | |
Is tower compliant with Rev G? | Yes | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1016457 | |
Coordinates (NAD83) | Latitude (NAD83) | 30° 16' 36.0" N- |
Longitude (NAD83) | 081° 33' 57.0" W- | |
Overall Structure Height | 1001.63 feet | |
Support Structure Height | 950.78 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 25.92 feet | |
Structure Type | TOWER - Free Standing or Guyed Structure | |
Tower Owner | IWG Towers Assets II, LLC | |
Date Constructed | 07/01/1988 |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | Study needed for documented tower |
Tower Reinforcements | Please select whether tower reinforcements are needed: | Major Reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | N/A |
Helicopter Services Required | Are helicopter services required? | No |
Name | Description |
---|---|
Remove Interim Antenna and STL |
Interim tower must be rigged a second time after assigned phase is complete to have the interim antenna, interim line, STL dish and waveguide removed from tower. |
Interim Tower Lease |
Monthly lease expenses at alternate site (InSite Tower) to support the top-mount interim antenna, TX line and STL for up to 12 months (see attached quote). |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Is this tower consider Complex? | Candelabra | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | Yes | |
Others Types of Users | Yes | |
Is tower documented for structural analysis? | Yes | |
Is tower compliant with Rev G? | No | |
Existing Tower Structure Registration | Do you have a tower registration number? | No |
ASR Number | ||
Coordinates (NAD83) | Latitude (NAD83) | 30° 16' 25.0" N- |
Longitude (NAD83) | 081° 33' 12.0" W- | |
Overall Structure Height | 303.70 feet | |
Support Structure Height | 268.90 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 15.20 feet | |
Structure Type | TOWER - Free Standing or Guyed Structure | |
Tower Owner | First Coast Tower Group | |
Date Constructed | 01/01/1985 |
Facility ID | Call Sign | Service |
---|---|---|
11893 | WJXX | DTV |
65046 | WTLV | DTV |
Users |
---|
Two-way users |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | Study needed for undocumented/poorly documented tower |
Tower Reinforcements | Please select whether tower reinforcements are needed: | Serious Reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | Candelabra |
Helicopter Services Required | Are helicopter services required? | Yes |
Name | Description |
---|---|
Existing Tower |
ASR is 1017604. The tower owner name was flagged by this application when it pre-filled so we had to manually enter. FAA & ASR required as a result of changing the top-mount antenna. |
Foundation Expansion |
Geotechnical findings indicate existing foundation loading design is not adequate to support the post-transition loads. |
Helicopter Site Staging Requirement |
Erickson Incorporated requires a 200 x 200 ft staging area for the helicopter lift. See attached quote to clear the site. |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 1500 | |
Explanation | It will be necessary to schedule and coordinate multiple vendors, complete progress reports, and update Schedule 399. Station does not have available personnel or personnel trained in project management for such complex projects. | |
Outside RF consulting Engineering Services | Perform engineering study for new channel assignment and antenna development | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
Do you have Distributed Transmission System engineering services? | N/A | |
Critical Facility | N/A | |
Terrain-Shielded Facility | N/A | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
NEPA Section 106 environmental review | Yes | |
Environmental Assessment | Yes | |
ASR Modification | Yes | |
FAA Consultation (including preparation of FAA Form 7460) | Yes | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Address transition timing and coordination issues w/ other stations and wireless providers | Yes | |
RF Field Engineering Services | Comprehensive coverage verification via field study | Yes |
RF exposure measurements | Yes | |
Additional Field Engineering Service | Yes | |
Number of Days | 45 | |
Justification | It will be necessary to survey the site, plan the equipment, develop specifications for purchasing, and oversee multiple vendor RF projects. Station does not have available personnel or personnel trained in such services. |
Name | Description |
---|---|
Intermod Study at Interim Site |
Tower owner requires an intermod study (see attached quote from InSite Towers, LLC) |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Facility Expenses | Name | N/A |
Other Distributed Transmission System Expenses Not listed | N/A | |
Name | N/A | |
Is Notification of a Medical Facility required as a result of DTV broadcasting? | Yes | |
Permit and Filing Costs | Local Zoning | No |
Non-zoning permits | Yes | |
BLM or NFS Coordination | No | |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | Yes | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | Yes | |
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? | Yes | |
Does this relocation require MVPD Notification of a Channel Change? | Yes |
Name | Description |
---|---|
STL System |
Microwave dish required for interim studio to transmitter link (STL) to be operated up to 12 months. Receiver, waveguide, licensing, etc. required for interim STL. See attached STL quotes. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $3,817,876.00 | $3,651,876.00 | N/A | $0.00 | N/A |
Total for all systems | $9,466,988.75 | $9,114,088.75 | N/A | $10,345.00 | N/A |
Interim Transmitter THU9EVO-30 | $2,175,776.00 | $2,088,676.00 | $0.00 | ||
Other Electrical Service: Additional services required to install new transmitter at alternate site (see attached quotes for monthly lease expenses; transmitter building costs; and electrical services costs). | $0.00 | $0.00 | Other electrical services are included in the attached Osborn Engineering quote for new 450 sq ft building at interim site. | N/A | N/A |
Service entrance 3 phase/800 amp/208 volt | $14,400.00 | $13,700.00 | N/A | N/A | N/A |
Switchgear - industrial 800 amp | $38,200.00 | $36,300.00 | N/A | N/A | N/A |
Transformer 3 phase/480v - 300 KVA | $36,800.00 | $35,000.00 | N/A | N/A | N/A |
2" Rigid Conduit and Wiring (Cost per foot) | $7,800.00 | $7,500.00 | N/A | N/A | N/A |
UHF - Liquid Cooled Solid State Transmitter 35 - 50 kW | $1,473,000.00 | $1,400,000.00 | N/A | N/A | N/A |
Other -- Building Addition Size: 450.0 | $355,176.00 | $355,176.00 | See attached letter from InSite Tower LLC (interim tower) stating that building must be provided and also see attached quote from Osborn Engineering for a new 450 sq ft building. Quote also includes required electrical services. | N/A | N/A |
10 Ton system | $38,900.00 | $37,000.00 | N/A | N/A | N/A |
UHF inside RF system including switching | $147,500.00 | $140,000.00 | N/A | N/A | N/A |
8-Pole Mask Filter | $64,000.00 | $64,000.00 | 8-pol mask filter required due to 1st-adjacent station issue. | N/A | N/A |
Primary Transmitter THU9EVO-24 | $1,642,100.00 | $1,563,200.00 | $0.00 | ||
Standby Exciter and Switch | $25,000.00 | $25,000.00 | N/A | N/A | N/A |
UHF - Liquid Cooled Solid State Transmitter 35 - 50 kW | $1,473,000.00 | $1,400,000.00 | N/A | N/A | N/A |
Other Electrical Service: Additional electrical services required for constructing the new LCSS TX while the existing IOT transmitter is in operation. | $25,000.00 | $25,000.00 | N/A | N/A | N/A |
Switchgear - industrial 800 amp | $38,200.00 | $36,300.00 | N/A | N/A | N/A |
Transformer 3 phase/480v - 300 KVA | $36,800.00 | $35,000.00 | N/A | N/A | N/A |
3" Rigid Conduit and Wiring (Cost per foot) | $5,200.00 | $4,900.00 | N/A | N/A | N/A |
10 Ton system | $38,900.00 | $37,000.00 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $1,207,800.00 | $1,182,800.00 | N/A | $0.00 | N/A |
Total for all systems | $9,466,988.75 | $9,114,088.75 | N/A | $10,345.00 | N/A |
Interim Antenna TFU-24WB C160 | $267,630.00 | $254,600.00 | $0.00 | ||
Sweep test of existing antenna | $6,730.00 | $6,400.00 | N/A | N/A | N/A |
UHF - High Power Top Mount (200-1000 kW), One station antenna, horizontally polarized | $247,000.00 | $235,000.00 | N/A | N/A | N/A |
Elbow complex, single channel, at antenna input, per 7 3/16. feedline (if needed) | $13,900.00 | $13,200.00 | N/A | N/A | N/A |
Interim Antenna TLSV-8BB | $310,290.00 | $303,800.00 | $0.00 | ||
Pattern scatter analysis for side mount high/med power antennas (if not included in antenna base cost) | $5,260.00 | $5,000.00 | See lease agreement for WTLV and WJXX with respect to reimbursement for interim VHF antenna. | N/A | N/A |
Side mount brackets for high power antennas (if not included in antenna base cost) | $23,150.00 | $22,000.00 | See lease agreement for WTLV and WJXX with respect to reimbursement for interim VHF antenna. | N/A | N/A |
Elbow complex, broadband, at antenna input, per 4 1/16. feedline (if needed) | $10,950.00 | $10,400.00 | See lease agreement for WTLV and WJXX with respect to reimbursement for interim VHF antenna. | N/A | N/A |
New combiner, cost per channel (without antenna) | $84,200.00 | $80,000.00 | See lease agreement for WTLV and WJXX with respect to reimbursement for interim VHF antenna. | N/A | N/A |
Sweep test of existing antenna | $6,730.00 | $6,400.00 | See lease agreement for WTLV and WJXX with respect to reimbursement for interim VHF antenna. | N/A | N/A |
UHF - High Power, Side Mount, basic slot antenna, 8 bay,, 83 kW input, directional,, horizontally polarized | $180,000.00 | $180,000.00 | See lease agreement for WTLV and WJXX with respect to reimbursement for interim VHF antenna. Budget amount comes from Widelity for a One-Station side-mount VHF station when in fact it is a Two-Station side-mount VHF antenna which costs more. | N/A | N/A |
Primary Antenna TFU-24GTH/VP-R TC 06SP | $629,880.00 | $624,400.00 | $0.00 | ||
Sweep test of existing antenna | $6,730.00 | $6,400.00 | N/A | N/A | N/A |
Elbow complex, broadband, at antenna input, per 8 3/16. feedline (if needed) | $18,950.00 | $18,000.00 | N/A | N/A | N/A |
New combiner, cost per channel (without antenna) | $84,200.00 | $80,000.00 | N/A | N/A | N/A |
UHF - High Power Top Mount Two Station antenna elliptically or circularly polarized | $520,000.00 | $520,000.00 | Widelity price for a top-mount, two-station broadband panel antenna (h-pol only) since there are no Widelity prices for a top-mount, two-station broadband slot antenna (h-pol only). Costs will be shared if WCWJ 1st priority CP application is granted. | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $712,535.00 | $677,850.00 | N/A | $0.00 | N/A |
Total for all systems | $9,466,988.75 | $9,114,088.75 | N/A | $10,345.00 | N/A |
Interim Transmission Line | $311,750.00 | $296,700.00 | $0.00 | ||
Rigid Transmission Line - copper, 7 3/16" | $311,750.00 | $296,700.00 | N/A | N/A | N/A |
Primary Transmission Line | $400,785.00 | $381,150.00 | $0.00 | ||
Rigid Transmission Line - copper, 8 3/16" | $400,785.00 | $381,150.00 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $3,027,118.51 | $2,920,718.51 | N/A | $3,687.50 | N/A |
Total for all systems | $9,466,988.75 | $9,114,088.75 | N/A | $10,345.00 | N/A |
Auxiliary Tower TOWER | $964,100.00 | $932,000.00 | $0.00 | ||
Major tower reinforcement/modifications | $421,000.00 | $400,000.00 | N/A | N/A | N/A |
Remove Interim Antenna and STL | $200,000.00 | $200,000.00 | Costs are based on removing the top-mount interim antenna, transmission line, STL dish and waveguide. | N/A | N/A |
Interim Tower Lease | $120,000.00 | $120,000.00 | See attached InSite Tower LLC quote. Costs are based on leasing space on the interim tower for 12 months. | N/A | N/A |
Tall Tower (greater than 500') | $210,500.00 | $200,000.00 | N/A | N/A | N/A |
Structural engineering tower load study for well documented tower | $12,600.00 | $12,000.00 | N/A | N/A | N/A |
Primary Tower TOWER | $2,063,018.51 | $1,988,718.51 | $3,687.50 | ||
Tower mapping for an undocumented/poorly documented tower and preparation of documentation necessary for tower load study | $26,300.00 | $25,000.00 | N/A | $3,687.50 | N/A |
Helicopter Site Staging Requirement | $91,134.51 | $91,134.51 | See attached quotes. Erickson Inc. requires a 200 x 200 ft clearing for lifts and the only way to achieve this is to have the area clear-cut and also requires a Strong Plank Steel Mat. | N/A | N/A |
Tower Helicopter Lift | $117,584.00 | $117,584.00 | See attached quote. The WJXT tower has history of using helicopter lifts since it is a complex candelabra. | N/A | N/A |
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) | $421,000.00 | $400,000.00 | N/A | N/A | N/A |
Serious tower reinforcement/modifications | $1,052,000.00 | $1,000,000.00 | Fully loaded, complex candelabra tower going from 222-F to 222-G in a Class III designated area near the coast. | N/A | N/A |
Foundation Expansion | $350,000.00 | $350,000.00 | N/A | N/A | N/A |
Existing Tower | $5,000.00 | $5,000.00 | FAA 7460-1, FAA 7460-2 and FCC Form 854 applications required. | N/A | N/A |
Actual Information Description | File Name |
---|---|
Major tower reinforcement/modifications | Information not provided. |
Remove Interim Antenna and STL | Information not provided. |
Interim Tower Lease | Information not provided. |
Tall Tower (greater than 500') | Information not provided. |
Structural engineering tower load study for well documented tower | Information not provided. |
Tower mapping for an undocumented/poorly documented tower and preparation of documentation necessary for tower load study | |
Helicopter Site Staging Requirement | Information not provided. |
Tower Helicopter Lift | Information not provided. |
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) | Information not provided. |
Serious tower reinforcement/modifications | Information not provided. |
Foundation Expansion | Information not provided. |
Existing Tower | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $485,000.00 | $464,750.00 | N/A | $6,657.50 | N/A |
Total for all systems | $9,466,988.75 | $9,114,088.75 | N/A | $10,345.00 | N/A |
Outside Professional Services | $485,000.00 | $464,750.00 | $6,657.50 | ||
Project management of the transition | $237,000.00 | $225,000.00 | N/A | $2,257.50 | N/A |
RF Exposure Measurements | $21,050.00 | $20,000.00 | N/A | $4,400.00 | N/A |
Intermod Study at Interim Site | $1,000.00 | $1,000.00 | See attached InSite Tower LLC quote for requited study. | N/A | N/A |
Additional Field Engineering Service, 45 Days | $90,000.00 | $90,000.00 | N/A | N/A | N/A |
Comprehensive coverage verification via field study, if needed | $84,200.00 | $80,000.00 | N/A | N/A | N/A |
FAA consultant, including cost of preparing FAA Form 7460 (Notice of Proposed Construction), if needed for height increase | $2,105.00 | $2,000.00 | N/A | N/A | N/A |
ASR modification (prepare FCC Form 854) | $2,105.00 | $2,000.00 | N/A | N/A | N/A |
Environmental Assessment, if triggered by NEPA Section 106 review or for certain structures over 450 feet | $10,520.00 | $10,000.00 | Soil issues from GEO report | N/A | N/A |
NEPA Section 106 environmental review, if needed | $6,310.00 | $6,000.00 | Soil issues from GEO report | N/A | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $5,260.00 | $5,000.00 | N/A | N/A | N/A |
Prepare request for Special Temporary Authorization | $2,050.00 | $1,500.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,580.00 | $1,500.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $3,155.00 | $3,000.00 | N/A | N/A | N/A |
Perform engineering study for new channel assignment and antenna development | $7,360.00 | $7,000.00 | N/A | N/A | N/A |
Address transition timing and coordination issues w/ other stations and wireless | $2,630.00 | $2,500.00 | N/A | N/A | N/A |
Prepare and or review reimbursement form | $2,630.00 | $2,500.00 | N/A | N/A | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $2,365.00 | $2,250.00 | N/A | N/A | N/A |
Attorney Fees - Prepare and File request for Special Temporary Authorization | $3,680.00 | $3,500.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Project management of the transition | |
RF Exposure Measurements | |
Intermod Study at Interim Site | Information not provided. |
Additional Field Engineering Service, 45 Days | Information not provided. |
Comprehensive coverage verification via field study, if needed | Information not provided. |
FAA consultant, including cost of preparing FAA Form 7460 (Notice of Proposed Construction), if needed for height increase | Information not provided. |
ASR modification (prepare FCC Form 854) | Information not provided. |
Environmental Assessment, if triggered by NEPA Section 106 review or for certain structures over 450 feet | Information not provided. |
NEPA Section 106 environmental review, if needed | Information not provided. |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Prepare request for Special Temporary Authorization | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Perform engineering study for new channel assignment and antenna development | Information not provided. |
Address transition timing and coordination issues w/ other stations and wireless | Information not provided. |
Prepare and or review reimbursement form | Information not provided. |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | Information not provided. |
Attorney Fees - Prepare and File request for Special Temporary Authorization | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $216,659.24 | $216,094.24 | N/A | $0.00 | N/A |
Total for all systems | $9,466,988.75 | $9,114,088.75 | N/A | $10,345.00 | N/A |
Other Expenses | $216,659.24 | $216,094.24 | $0.00 | ||
MVPD Notification of Channel Change | $2,000.00 | $2,000.00 | N/A | N/A | N/A |
Develop and air announcement of upcoming channel change | $10,000.00 | $10,000.00 | N/A | N/A | N/A |
Equipment Storage | $25,000.00 | $25,000.00 | N/A | N/A | N/A |
Equipment Delivery and Handling Charges | $25,000.00 | $25,000.00 | N/A | N/A | N/A |
Disposal Costs (for equipment and other waste, net of any salvage value) | $25,000.00 | $25,000.00 | N/A | N/A | N/A |
Non-zoning permits | $25,000.00 | $25,000.00 | N/A | N/A | N/A |
FCC Filing Fees - Special Temporary Authorization request | $195.00 | $190.00 | N/A | N/A | N/A |
DTV Medical Facility Notification | $11,550.00 | $11,000.00 | N/A | N/A | N/A |
STL System | $92,579.24 | $92,579.24 | STL required at interim site. See attached STL quotes from Vernick Technology, Inc. and Data Flow Communications. | N/A | N/A |
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $325.00 | N/A | N/A | N/A |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $9,466,988.75 | $9,114,088.75 | $10,345.00 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | No |
Construction of final facilities or all necessary modifications are complete. | No |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Jeffrey C Gehman Engineering Associate 02/27/2018 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Jeffrey C Gehman Engineering Associate 02/27/2018 |