FCC Form 399: Reimbursement Request

Approved by OMB 3060-1178
Go to the Federal Communications Commission homepage at www.fcc.gov

(REFERENCE COPY - Not for submission) FCC Form 399: Reimbursement Request

Facility ID:
42359
Service:
DTV
Call Sign:
KTXD-TV
Channel:
23 (UHF)
File Number:
0000028579
FRN:
0027171693
Date Submitted:
07/12/2017

Applicant Information

Back to Top

Applicant Name, Type, and Contact Information

Applicant Address Phone Email Applicant Type

KTXD LICENSE COMPANY, LLC

Doing Business As: KTXD LICENSE COMPANY, LLC

Jonathan Dietz

15455 DALLAS PARKWAY

SUITE 100

ADDISON, TX 75001

United States

+1 (214) 628-9900 jdietz@lbc-texas.com Limited Liability Company

Reimbursement Contact Information

Reimbursement Contact Name and Information

Applicant Address Phone Email

[Confidential]

 

 

 


Preparer Contact Information

Back to Top

Preparer Contact Name and Information

Applicant Address Phone Email

David Sanderford

Marsand, Inc.

David Sanderford

1957 Reynolds Dr

Azle, TX 76020

United States

+1 (817) 783-5566 david@marsand.com

Broadcaster Information and Transition Plan

Back to Top
Question Response
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. Yes
Briefly describe transition plan KTXD will build out it post-auction facility at the American Tower Milton Site using a shared channel combiner, transmission line and antenna. The station must purchase a new main transmitter, mask filter, interior RF components, electrical and HVAC.

Transmitters

Back to Top
Section Question Response
Transmitter Related Expenses Do you have transmitter related expenses? Yes

Auxiliary Transmitter

Back to Top

Add Transmitter Information

Section Question Response
Existing Transmitter Description Type of change Retune Existing
Use Auxiliary (Backup)
Ownership Owned
Owner N/A
Is this transmitter currently shared with another station? No
Is this transmitter currently in operating condition? Yes
Existing Transmitter Manufacturer and Type Manufacturer Harris
Model ULX-4700AT
Year 2009
Type Solid State
Solid State Cooling Liquid Cooled
Solid State Power capacity 5 kW

Auxiliary Transmitter

Back to Top

Retuning Transmitter Costs

Section Question Response
New IOT Tubes Number of Tubes (including accessories) needed N/A
New Mask Filter
Power 7 kW
Other Power N/A
New Exciter Is a new exciter needed? No

Auxiliary Transmitter

Back to Top

Other Transmitter Costs

Section Question Response
Electrical Service Service Entrance (3 phases 800A 208V) No
Switchgear (industrial 800 amp) No
Transformer (480V) No
Power N/A
Rigid Conduit and Wiring No
Size N/A
Length N/A
Other Electrical Service No
Description N/A
HVAC Service Does the replacement transmitter require HVAC Service? No
Type N/A
Size N/A
Other Size N/A
Transmitter Building Addition/Modification or Leasehold Improvement Does the Transmitter Building require an addition, modification, other leashold improvement? No
Size N/A
Channel 14 Costs Is an RF Consulting Engineer needed? N/A
Is a channel 14 Mask Filer needed? N/A
Is additional field engineering time needed? N/A
Number of Days N/A

Auxiliary Transmitter

Back to Top

Other Transmitter Cost Not Listed

Information not provided.

Primary Transmitter

Back to Top

Existing Transmitter Information

Section Question Response
Existing Transmitter Description Type of change Purchase New
Use Primary (Main)
Description of Use N/A
Ownership Owned
Owner N/A
Site N/A
Is this transmitter currently shared with another station? No
Is this transmitter currently in operating condition? Yes
Existing Transmitter Manufacturer and Type Manufacturer
Model CDP3100P1
Year 2005
Type Inductive Output Tube
IOT Power Type Single
Power Capacity 21 kW

Primary Transmitter

Back to Top

New Transmitter Costs

Section Question Response
New Transmitter Use Primary (Main)
Change Type Purchase New
Is this a request for upgraded equipment? Yes
Manufacturer
Model THU9-24Evo
Transmitter Type Solid State
Solid State Cooling Liquid Cooled
Solid State Power capacity 37 kW
Justification for New Transmitter Existing transmitter is not supported for retuning. Station plans to file for maximization as stated in the filed application for minor modification to better match existing service area.

Primary Transmitter

Back to Top

Other Transmitter Costs

Section Question Response
Electrical Service Service Entrance (3 phases 800A 208V) No
Switchgear (industrial 800 amp) No
Transformer (480V) No
Power N/A
Rigid Conduit and Wiring No
Size N/A
Length N/A
Other Electrical Service Yes
Description Electrical installation for new transmitter.
HVAC Service Does the replacement transmitter require HVAC Service? Yes
Type Cooling Only
Size 25 tons
Other Size N/A
Transmitter Building Addition/Modification or Leasehold Improvement Does the Transmitter Building require an addition, modification, other leashold improvement? Yes
Size 3300.0 square feet
Channel 14 Costs Is an RF Consulting Engineer needed? N/A
Is a channel 14 Mask Filer needed? N/A
Is additional field engineering time needed? N/A
Number of Days N/A

Primary Transmitter

Back to Top

Other Transmitter Cost Not Listed

Name Description

Ice Shield

Ice Protection over the mechanical slab and the equipment for new HVAC units, heat exchangers and repack broadcasters equipment to be installed.

Antennas

Back to Top
Section Question Response
Antenna Related Expenses Do you have antenna related expenses? Yes

Primary Antenna

Back to Top

Existing Antenna Information

Section Question Response
Existing Antenna Description Type of change Lease New
Antenna Use Primary (Main)
Description of Use N/A
Ownership Leased
Owner ATC
Site N/A
Is the existing antenna shared with another station or stations? Yes
Is the existing antenna directional? Yes
Is antenna in operating condition? Yes
Is antenna located on or in close proximity to an antenna farm? Yes
Existing Antenna Manufacturer and Type Class Full Power
Mounting Top Mount
Antenna position in stack Not in Stack
Polarization Horizontal
Type Broadband Panel
Number of Stations Supported 4
Number of Panels 36
Design power capacity in use 92.5 %
Lower Limit 506.00 MHz
Upper Limit 698.00 MHz
Other Antenna Type N/A
ERP: 600.0 kW
Manufacturer
Model PHP36C
Year 2003

Facility ID's and Call Signs of all stations with whom the antenna is shared.

Facility ID Call Sign
17037 KDFI
49326 KDTN
67910 KDTX-TV

Primary Antenna

Back to Top

New Antenna Costs

Section Question Response
New Antenna Description Use Primary (Main)
Description of Use N/A
Change Type Lease New
Is this a request for upgraded equipment? Yes
Ownership Leased
Owner ATC
Is antenna shared? Yes
Is antenna directional? Yes
Will antenna be located on or in close proximity to an antenna farm? Yes
New Antenna Manufacturer and Types Class Full Power
Mounting Top Mount
Antenna position in stack Not in Stack
Polarization Elliptical
Type Broadband Panel
Number of Stations Supported 4
Number of Panels/Bays 42
Lower Limit 488.00 MHz
Upper Limit 608.00 MHz
Design power capacity in use 31.0 %
Other Antenna Type N/A
ERP: 130.0 kW
Manufacturer
Model TUM-C3-AP-14/42H-2-R-T
Year 2018
Justification for New Antenna Please see attached ATC Transition Plan

Primary Antenna

Back to Top

Other Antenna Costs

Section Question Response
Combiner for Shared Antenna Do you need a Combiner for a Shared Antenna? Yes
Type New
Number of channels supported 4
Frequencies of channels supported RF channel
Frequency N/A
Do you need a combiner output splitter/switcher for dual feed lines? No
Elbow Complex Do you require the separate purchase of the Elbow Complex? Yes
Broadband or Single Channel? Broadband
Feed Line Size 7 3/16 inches inches
Side Mount Brackets Do you require the separate purchase of side mount brackets for a high power antenna? No
Pattern Scatter Analysis Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? No
Sweep Test Do you require the sweep testing of transmission line and antenna? Yes

Enter a list of RF channel numbers.

RF Channel Number
18
19
23
29

Primary Antenna

Back to Top

Other Antenna Cost Not Listed

Name Description

Combiner Installation

Installation of the combiner; Dual chain combiner system, Single chain of 2 constant impedance waveguide modules, and/or single chain of 2 directional filter modules per Dielectric layout plus a third low power filter for the wideband port.

Transmission Line

Back to Top
Section Question Response
Transmission Line Related Expenses Do you have transmission line related expenses? Yes

Primary Transmission Line

Back to Top

Existing Transmission Line

Section Question Response
Existing Transmission Line Description Type of change Lease New
Use Primary (Main)
Description of Use N/A
Ownership Leased
Owner ATC
Site N/A
Is the existing transmission line shared with another station or stations? Yes
Is Transmission Line in operating condition? Yes
Existing Transmission Line Manufacturer and Type Manufacturer
Type Rigid
Diameter 8 3/16 inches
Other Diameter N/A
Segment Length Broadband
Other Segment Length N/A
Number of parallel runs 1
Length 1507 feet per run

Facility ID's and Call Signs of all stations with whom the transmission line is shared.

Facility ID Call Sign
67910 KDTX-TV
17037 KDFI
49326 KDTN

Primary Transmission Line

Back to Top

New Transmission Line

Section Question Response
New Transmission Line Costs Use Primary (Main)
Description of Use N/A
Change Type Lease New
Is this a request for upgraded equipment? Yes
Type Rigid
Diameter 7 3/16 inches
Other Diameter N/A
Segment Length Broadband
Other Segment Length N/A
Number of parallel runs 2
Length 1650 feet per run
Justification for New Transmission Line Please see attached ATC Transition Plan

Primary Transmission Line

Back to Top

Other Transmission Line Expenses Not Listed

Name Description

Transmission Line Bridge

New Ice Bridge required to support new transmission lines from all four repack tenants space to tower, estimated to be 200 linear ft. This cost includes the materials, foundations and installation.

Tower Equipment And Rigging Costs

Back to Top
Section Question Response
Tower Equipment or Rigging Costs Changes Do you have tower equipment or rigging costs changes? Yes

Primary Tower

Back to Top

Existing Tower

Section Question Response
Existing Tower Description Type of change Modify Existing
Tower Use Primary (Main)
Description of Use N/A
Ownership Leased
Is this tower consider Complex? Candelabra
Is this tower currently shared with any other stations? Yes
One or more FM, AM or TV radio broadcaster(s) Yes
Others Types of Users Yes
Is tower documented for structural analysis? No
Is tower compliant with Rev G? Unknown
Existing Tower Structure Registration Do you have a tower registration number? Yes
ASR Number 1055009
Coordinates (NAD83) Latitude (NAD83) 32° 35' 22.0" N-
Longitude (NAD83) 096° 58' 12.9" W-
Overall Structure Height 1550.83 feet
Support Structure Height 1453.07 feet
Ground Elevation Above Mean Sea Level (AMSL) 829.71 feet
Structure Type GTOWER - Guyed Structure Used for Communication Purposes
Tower Owner American Tower, LLC
Date Constructed 11/04/2008

FM, AM or TV radio broadcasters. Facility ID's, Call Signs and Services of other broadcast stations with whom the tower is shared

Facility ID Call Sign Service
35841 KUVN-DT DTV

Other Types of Users

Users
KVFW-LD CH38
KODF-LD CH27
KNAV-LP CH22-
KJJM-LD CH34
KHPK-LD CH28
KATA-CD CH50
K31GL-D CH31

Primary Tower

Back to Top

Tower Modification Costs

Section Question Response
Engineering Study Please what type of engineering study is required, if any: Study needed for tower with candelabra
Tower Reinforcements Please select whether tower reinforcements are needed: Serious Reinforcements needed

Primary Tower

Back to Top

Tower Rigging Costs

Section Question Response
Tower Rigging Costs Complex Tower Candelabra
Helicopter Services Required Are helicopter services required? No

Primary Tower

Back to Top

Other Tower Expenses Not Listed

Name Description

Tower Permit Drawing Package

The generation of a construction drawing package for one (1) broadcasters/customers.

Construction project management Tower Modifications Reinforcements and Facilities

(60) hours on Modification project management and RF installation project management.

Ground and Building AandE Permit Drawing Package

The generation of a construction drawing package for one (1) broadcasters/customers.

Outside Professional Services Costs

Back to Top
Section Question Response
Outside Project Management Services Do you require outside project management services? Yes
Number of Hours 450
Explanation The station will contract for Project Management services to handle the complete project. It does not have personnel available for any of these tasks, nor is the staff trained to provide any of these services.
Outside RF consulting Engineering Services Perform engineering study for new channel assignment and antenna development Yes
Prepare engineering section of Form FCC Construction Permit Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare engineering section of Form FCC License to Cover Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare request for Special Temporary Authority No
Quantity N/A
Do you have Distributed Transmission System engineering services? N/A
Critical Facility N/A
Terrain-Shielded Facility N/A
Attorney and Other Outside Consulting Services Prepare and file Form FCC Construction Permit Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare and file Form FCC License to Cover Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare request for Special Temporary Authority No
Quantity N/A
NEPA Section 106 environmental review Yes
Environmental Assessment No
ASR Modification No
FAA Consultation (including preparation of FAA Form 7460) No
Negotiation of Lease and other Matter for Shared Locations Yes
Prepare or Review FCC Form 399 for Reimbursement Yes
Address transition timing and coordination issues w/ other stations and wireless providers Yes
RF Field Engineering Services Comprehensive coverage verification via field study Yes
RF exposure measurements Yes
Additional Field Engineering Service No
Number of Days N/A
Justification N/A

Outside Professional Services Costs

Back to Top

Other Professional Services Expenses Not Listed

Name Description

RF System Test

Testing of the combiner to ensure all one (1) frequencies are tuned for optimal patterns.

Migratory Bird Assessment Permitting

Migratory Bird Assessment Permitting

Site Coordination Meeting

Site coordination meetings with all broadcasters, contractors and vendors involved with the site deliveries and construction.

Other Expenses

Back to Top
Section Question Response
AM Pattern Disturbance Is an Impact Study needed? No
Is Remediation needed? No
Facility Expenses Name N/A
Other Distributed Transmission System Expenses Not listed N/A
Name N/A
Is Notification of a Medical Facility required as a result of DTV broadcasting? Yes
Permit and Filing Costs Local Zoning Yes
Non-zoning permits No
BLM or NFS Coordination No
FCC Construction Permit Minor Change No
FCC License to Cover Application No
FCC Special Temporary Authority Application No
Other Miscellaneous Expenses Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? Yes
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? Yes
Does this relocation require Equipment Storage? No
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? No
Does this relocation require MVPD Notification of a Channel Change? Yes

Other Expenses

Back to Top

Other Expenses Not Listed

Name Description

Tree Clearing

This cost is for the removal of trees and vegetation to ensure the proper clearance of taglines and laydown areas, required for construction.

Construction and Electrical Permits

2% construction cost, excluding the material and equipment for electrical and building permits.

Site Security

Site security for installation and storage of Transmission line and materials for 57 days X 12 hours. The materials are a high risk of theft due to the material makeup such as copper, brass and aluminum.

Cost Information

Back to Top

Transmitters

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $1,829,510.00 $1,746,500.00 N/A $0.00 N/A
Total for all systems $5,946,440.00 $5,666,100.00 N/A $0.00 N/A
Primary Transmitter THU9-24Evo $1,718,100.00 $1,640,600.00 $0.00
UHF - Liquid Cooled Solid State Transmitter 35 - 50 kW $1,473,000.00 $1,400,000.00 N/A N/A N/A
Other Electrical Service: Electrical installation for new transmitter. $30,000.00 $30,000.00 Electrical distribution to the new transmitter. Parts and installation. N/A N/A
Other -- Building Addition Size: 3300.0 $83,600.00 $83,600.00 Please see attached ATC Transition Plan N/A N/A
Ice Shield $40,000.00 $40,000.00 Please see attached ATC Transition Plan N/A N/A
25 Ton system $91,500.00 $87,000.00 Please see attached ATC Transition Plan N/A N/A
Auxiliary Transmitter ULX-4700AT $111,410.00 $105,900.00 $0.00
UHF and VHF - minor banding issues $105,200.00 $100,000.00 Catalog N/A N/A
7 kW mask filter $6,210.00 $5,900.00 Catalog N/A N/A

Components

Information not provided.

Cost Information

Back to Top

Antennas

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $1,204,030.00 $1,144,650.00 N/A $0.00 N/A
Total for all systems $5,946,440.00 $5,666,100.00 N/A $0.00 N/A
Primary Antenna TUM-C3-AP-14/42H-2-R-T $1,204,030.00 $1,144,650.00 $0.00
Combiner Installation $6,250.00 $6,250.00 Installation of the combiner; Dual chain combiner system, Single chain of 2 constant impedance waveguide modules, and/or single chain of 2 directional filter modules per Dielectric layout plus a third low power filter for the wideband port. N/A N/A
UHF - High Power Top Mount (200-1000 kW), Four Station broadband panel antenna, elliptically or circularly polarized $1,090,000.00 $1,036,000.00 14 Bays by 4 around with lower # on face 4, 48 elements total, 4 sided assembly mast broadband antenna to transmit the new repack frequencies. N/A N/A
Elbow complex, broadband, at antenna input, per 7 3/16. feedline (if needed) $16,850.00 $16,000.00 Two (2) Elbow complex for the input of the new Broadband antenna N/A N/A
Sweep test of existing antenna $6,730.00 $6,400.00 RF system testing for two (2) lines and one (1) antenna. N/A N/A
New combiner, cost per channel (without antenna) $84,200.00 $80,000.00 Dual chain of 4 constant impedance waveguide modules, each and/or dual chains of 4 directional filter modules per Dielectric layout. one (1) transmitters will go into the combiner. N/A N/A

Components

Information not provided.

Cost Information

Back to Top

Transmission Line

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $1,121,400.00 $1,068,600.00 N/A $0.00 N/A
Total for all systems $5,946,440.00 $5,666,100.00 N/A $0.00 N/A
Primary Transmission Line $1,121,400.00 $1,068,600.00 $0.00
Transmission Line Bridge $22,500.00 $22,500.00 New Ice Bridge required to support new transmission lines from all four repack tenants space to tower, estimated to be 200 linear ft. This cost includes the materials, foundations and installation. N/A N/A
Rigid Transmission Line - copper, 7 3/16" broadband $1,098,900.00 $1,046,100.00 Two (2) 7-3/16" Broadband Transmission lines, at 1650' each for a total of 3300', six (6) elbows (3 elbows each transmission line), and nitrogen generator to accommodate the repack assigned frequencies. This cost includes the for pressurization of the br N/A N/A

Components

Information not provided.

Cost Information

Back to Top

Tower Equipment and Rigging Costs

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $1,509,900.00 $1,435,900.00 N/A $0.00 N/A
Total for all systems $5,946,440.00 $5,666,100.00 N/A $0.00 N/A
Primary Tower GTOWER $1,509,900.00 $1,435,900.00 $0.00
Ground and Building AandE Permit Drawing Package $4,700.00 $4,700.00 The generation of a construction drawing package for one (1) broadcasters/customers. N/A N/A
Tower Permit Drawing Package $4,700.00 $4,700.00 The generation of a construction drawing package for one (1) broadcasters/customers. N/A N/A
Construction project management Tower Modifications Reinforcements and Facilities $7,500.00 $7,500.00 (60) hours on Modification project management and RF installation project management. N/A N/A
Structural engineering tower load study for a documented tower with candelabra $20,000.00 $19,000.00 Structural tower mapping to ensure the proper structural information is relayed to engineering. Rigorous Structural analysis to assess the structural capacity and modifications needed to accommodate the repacked equipment. N/A N/A
Serious tower reinforcement/modifications $1,052,000.00 $1,000,000.00 It is expected that the additional loads imposed on the tower by the repack project will cause the tower to fail. The structural failure is expected to be in the serious category requiring replacement of several structural members and guy wires N/A N/A
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) $421,000.00 $400,000.00 Includes removing 3 existing antennas, associated transmission lines, installing broadband antenna, two transmission lines, all required tower bracket material to support additional transmission line on tower, and one 35' antenna stub section. N/A N/A

Components

Information not provided.

Cost Information

Back to Top

Outside Professional Services

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $218,700.00 $208,100.00 N/A $0.00 N/A
Total for all systems $5,946,440.00 $5,666,100.00 N/A $0.00 N/A
Outside Professional Services $218,700.00 $208,100.00 $0.00
Prepare and or review reimbursement form $2,630.00 $2,500.00 N/A N/A N/A
Address transition timing and coordination issues w/ other stations and wireless $2,630.00 $2,500.00 N/A N/A N/A
Perform engineering study for new channel assignment and antenna development $7,360.00 $7,000.00 N/A N/A N/A
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application $3,155.00 $3,000.00 N/A N/A N/A
Prepare engineering section of FCC Form 2100 (main), License to Cover Application $1,580.00 $1,500.00 N/A N/A N/A
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application $5,260.00 $5,000.00 N/A N/A N/A
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application $2,365.00 $2,250.00 N/A N/A N/A
Attorney Fees - Negotiation of lease and other matters for shared locations $4,210.00 $4,000.00 N/A N/A N/A
Site Coordination Meeting $2,500.00 $2,500.00 Site coordination meetings with all broadcasters, contractors and vendors involved with the site deliveries and construction. N/A N/A
Project management of the transition $71,100.00 $67,500.00 N/A N/A N/A
RF System Test $4,000.00 $4,000.00 Testing of the combiner to ensure all one (1) frequencies are tuned for optimal patterns. N/A N/A
Migratory Bird Assessment Permitting $350.00 $350.00 N/A N/A N/A
NEPA Section 106 environmental review, if needed $6,310.00 $6,000.00 N/A N/A N/A
Comprehensive coverage verification via field study, if needed $84,200.00 $80,000.00 N/A N/A N/A
RF Exposure Measurements $21,050.00 $20,000.00 N/A N/A N/A

Components

Information not provided.

Cost Information

Back to Top

Other Expenses

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $62,900.00 $62,350.00 N/A $0.00 N/A
Total for all systems $5,946,440.00 $5,666,100.00 N/A $0.00 N/A
Other Expenses $62,900.00 $62,350.00 $0.00
DTV Medical Facility Notification $11,550.00 $11,000.00 N/A N/A N/A
Local Zoning $4,700.00 $4,700.00 Preparation and submission of the needed forms for permits, on behalf of the one (1) broadcasters for jurisdictional permits, required for electrical, building and other required tasks associated with the install of the equipment in the transmitter space N/A N/A
Disposal Costs (for equipment and other waste, net of any salvage value) $16,500.00 $16,500.00 Pre-auction channel transmitter and interior RF system dismantling, removal and disposal including coolant and oil reclamation. N/A N/A
Tree Clearing $1,600.00 $1,600.00 This cost is for the removal of trees and vegetation to ensure the proper clearance of taglines and laydown areas, required for construction. N/A N/A
Construction and Electrical Permits $10,000.00 $10,000.00 2% construction cost, excluding the material and equipment for electrical and building permits. N/A N/A
Site Security $8,550.00 $8,550.00 Site security for installation and storage of Transmission line and materials for 57 days X 12 hours. The materials are a high risk of theft due to the material makeup such as copper, brass and aluminum. N/A N/A
Equipment Delivery and Handling Charges $5,000.00 $5,000.00 Material/equipment, delivery and offloading by third party contractors. Forklifts, manpower and costs accumulated for the unloading of transmission line, antenna delivery and/or other building material needed to complete the construction of the site. N/A N/A
MVPD Notification of Channel Change $5,000.00 $5,000.00 N/A N/A N/A

Components

Information not provided.

Cost Information

Back to Top

Grand Total

Predetermined
Cost Estimate
Estimated Cost Actual Cost
Total for all systems $5,946,440.00 $5,666,100.00 $0.00

Reimbursement Status

Back to Top
Question Response
The facility has ceased operating on its pre-auction channel. No
Construction of final facilities or all necessary modifications are complete. No
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. No

Certification

Back to Top
Section Question Response
Submission of Estimated Expenses Statements

WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT.

  1. The Authorized Person signing below certifies that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity.

  2. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  3. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  4. The above-named entity certifies that the equipment and services paid for with money from the TV Broadcaster Relocation Fund are necessary to change channels (broadcasters) or to continue to carry the signal of a broadcaster that changes channels (MVPD).

  5. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  6. The above-named entity certifies that it will maintain and provide to the Commission detailed records, including receipts, of all costs eligible for reimbursement actually incurred.

  7. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  8. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a pre-requisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

Jonathan Dietz

CFO


07/12/2017

Attachments