Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
VALLEY PUBLIC TELEVISION, INC., DBA VALLEYPBS Doing Business As: VALLEY PUBLIC TELEVISION, INC., D/B/A/ VALLEYPBS |
Phyllis Brotherton 1544 VAN NESS AVENUE FRESNO, CA 93721 United States |
+1 (559) 266-1800 | pbrotherton@valleypbs.org | Corporation |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Ann Bobeck Legal Counsel Covington and Burling LLP |
Ann Bobeck One CityCenter 850 10th Street NW Washington , DC 20001 United States |
+1 (202) 662-5719 | abobeck@cov.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | No |
Briefly describe transition plan | Decommission side mount antenna to install new aux antenna that will be connected to current Ch 40 transmitter. Decommission top mount Ch 40 Andrew antenna, install top mount Ch 32 ERI antenna. install ULXTE-16 Ch 32, test, switch over. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | Diamond | |
Year | 2004 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power Capacity | 7.8 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Manufacturer | ||
Model | ULXTE-16 | |
Transmitter Type | Solid State | |
Solid State Cooling | Liquid Cooled | |
Solid State Power capacity | 10.8 kW | |
Justification for New Transmitter | The current transmitter (Harris - Diamond) can not be re-tuned to be used for the new frequency. Kindly find attached a letter from the manufacturer that states this. |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Power | N/A | |
Rigid Conduit and Wiring | No | |
Size | N/A | |
Length | N/A | |
Other Electrical Service | Yes | |
Description | Grounding work and other electrical work | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Type | N/A | |
Size | N/A | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Size | N/A | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Name | Description |
---|---|
Uninstall fees |
Uninstalling the current diamond transmitter to make room for the new transmitter |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Auxiliary (Backup) | |
Description of Use | Secondary | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is this antenna currently shared with any other stations? | No | |
Is this antenna directional? | Yes | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | Class | Full Power |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Elliptical | |
Type | Other | |
Number of Stations Supported | N/A | |
Number of Panels | N/A | |
Design power capacity in use | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Other Antenna Type | Superturnstile Antenna | |
ERP: | 30.0 kW | |
Manufacturer | ||
Model | UTV-11/2/P UHF | |
Year | 2017 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Auxiliary (Backup) |
Description of Use | backup | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | No | |
Is antenna directional? | No | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Types | Class | Full Power |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Broadband Slot | |
Number of Stations Supported | 1 | |
Number of Panels/Bays | 2 | |
Lower Limit | 470.00 MHz | |
Upper Limit | 860.00 MHz | |
Design power capacity in use | 50.0 % | |
Other Antenna Type | N/A | |
ERP: | 30.0 kW | |
Manufacturer | ||
Model | UTV-11/2/P UHF | |
Year | 2017 | |
Justification for New Antenna | A backup antenna is needed when we test Ch 32 transmitter but are still transmitting on Ch 40, and when the new top mount antenna is to be installed |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | No |
Type | ||
Number of channels supported | N/A | |
Frequencies of channels supported | N/A | |
Frequency | N/A | |
Do you need a combiner output splitter/switcher for dual feed lines? | N/A | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | Yes |
Broadband or Single Channel? | Single Channel | |
Feed Line Size | 6 1/8 inches inches | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | Yes |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | Yes |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is this antenna currently shared with any other stations? | No | |
Is this antenna directional? | Yes | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | Class | Full Power |
Mounting | Top Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Elliptical | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels | N/A | |
Design power capacity in use | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Other Antenna Type | N/A | |
ERP: | 213.0 kW | |
Manufacturer | ||
Model | ATW 18H6-ETC3-32H | |
Year | 2017 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | No | |
Is antenna directional? | No | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Types | Class | Full Power |
Mounting | Top Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Elliptical | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels/Bays | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Design power capacity in use | N/A | |
Other Antenna Type | N/A | |
ERP: | 213.0 kW | |
Manufacturer | ||
Model | ATW18H6-ETC3-32H | |
Year | 2017 | |
Justification for New Antenna | Current antenna cannot broadcast on new frequency range |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | No |
Type | ||
Number of channels supported | N/A | |
Frequencies of channels supported | N/A | |
Frequency | N/A | |
Do you need a combiner output splitter/switcher for dual feed lines? | N/A | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | Yes |
Broadband or Single Channel? | Single Channel | |
Feed Line Size | 6 1/8 inches inches | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | No |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Name | Description |
---|---|
Uninstall fees |
Uninstall current antenna |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Utilize Existing |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | Harris |
Type | Waveguide | |
Diameter | N/A | |
Other Diameter | N/A | |
Segment Length | N/A | |
Other Segment Length | N/A | |
Number of parallel runs | 6 | |
Length | 12 feet per run |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Utilize Existing |
Use | Auxiliary (Backup) | |
Description of Use | Backup | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is this transmission currently shared with any other stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | Harris |
Type | Waveguide | |
Diameter | N/A | |
Other Diameter | N/A | |
Segment Length | N/A | |
Other Segment Length | N/A | |
Number of parallel runs | 4 | |
Length | 12 feet per run |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Leased | |
Is this tower consider Complex? | Terrain Constrained | |
Is this tower currently shared with any other stations? | No | |
One or more FM, AM or TV radio broadcaster(s) | N/A | |
Others Types of Users | N/A | |
Is tower documented for structural analysis? | Yes | |
Is tower compliant with Rev G? | Yes | |
Existing Tower Structure Registration | Do you have a tower registration number? | No |
ASR Number | ||
Coordinates (NAD83) | Latitude (NAD83) | 36° 44' 45.0" N- |
Longitude (NAD83) | 119° 16' 55.0" W- | |
Overall Structure Height | 244.75 feet | |
Support Structure Height | 199.80 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 3640.75 feet | |
Structure Type | NTOWER - Multiple Structures | |
Tower Owner | Valley Public Television, Inc | |
Date Constructed | 01/01/1953 |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | Study needed for undocumented/poorly documented tower |
Tower Reinforcements | Please select whether tower reinforcements are needed: | Minor Reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | Terrain constrained |
Helicopter Services Required | Are helicopter services required? | Yes |
Name | Description |
---|---|
Tower maintinance |
Mainly for tower grounding, lighting, etc. |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 120 | |
Explanation | We do not have the qualified staff to manage the scale and complexity of this type of project. | |
Outside RF consulting Engineering Services | Perform engineering study for new channel assignment and antenna development | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | Yes | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Quantity | N/A | |
Do you have Distributed Transmission System engineering services? | N/A | |
Critical Facility | N/A | |
Terrain-Shielded Facility | N/A | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | Yes | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | Yes | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Quantity | N/A | |
NEPA Section 106 environmental review | No | |
Environmental Assessment | No | |
ASR Modification | No | |
FAA Consultation (including preparation of FAA Form 7460) | No | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Address transition timing and coordination issues w/ other stations and wireless providers | Yes | |
RF Field Engineering Services | Comprehensive coverage verification via field study | Yes |
RF exposure measurements | Yes | |
Additional Field Engineering Service | Yes | |
Number of Days | 3 | |
Justification | We do not have the qualified staff with the expertise to do this in-house. |
Name | Description |
---|---|
transmission line sweep |
We swiped the transmission lines for the top mount and side mount antenna. |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Facility Expenses | Name | N/A |
Other Distributed Transmission System Expenses Not listed | N/A | |
Name | N/A | |
Is Notification of a Medical Facility required as a result of DTV broadcasting? | No | |
Permit and Filing Costs | Local Zoning | Yes |
Non-zoning permits | Yes | |
BLM or NFS Coordination | No | |
FCC Construction Permit Minor Change | Yes | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | Yes | |
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? | Yes | |
Does this relocation require MVPD Notification of a Channel Change? | Yes |
Name | Description |
---|---|
Zoning and local permits |
fees for local permit by Fresno county planning commission |
Tower Lease Agreement modifications |
renegotiate the lease for the current tower site and transmitter |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $421,075.00 | $421,075.00 | N/A | $0.00 | N/A |
Total for all systems | $1,830,617.95 | $1,385,342.95 | N/A | $0.00 | N/A |
Primary Transmitter ULXTE-16 | $421,075.00 | $421,075.00 | $0.00 | ||
- Liquid Cooled Solid State Transmitter 10.8 kW | $344,406.00 | $344,406.00 | This will include installation fees and a new mask filter as well. | N/A | N/A |
Other Electrical Service: Grounding work and other electrical work | $10,000.00 | $10,000.00 | N/A | N/A | N/A |
Uninstall fees | $66,669.00 | $66,669.00 | this will also include the uninstall fees for the antenna as well | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $442,823.95 | $476,553.95 | N/A | $0.00 | N/A |
Total for all systems | $1,830,617.95 | $1,385,342.95 | N/A | $0.00 | N/A |
Primary Antenna ATW18H6-ETC3-32H | $370,921.49 | $386,991.49 | $0.00 | ||
- High Power, Top Mount, basic slot antenna, 213 kW input, elliptically or circularly polarized | $209,956.49 | $209,956.49 | new antenna with gear | N/A | N/A |
Elbow complex, single channel, at antenna input, per 6 1/8. feedline (if needed) | $12,300.00 | $12,000.00 | new elbow complex needed at the top of the tower | N/A | N/A |
Sweep test of existing antenna | $6,730.00 | $23,100.00 | sweep test for existing TX line and site survey | N/A | N/A |
Uninstall fees | $141,935.00 | $141,935.00 | Will include uninstall of old antenna and install of new antenna | N/A | N/A |
Auxiliary Antenna UTV-11/2/P UHF | $71,902.46 | $89,562.46 | $0.00 | ||
- High Power, Side Mount, basic slot antenna, 2 bay,, 30 kW input, horizontally polarized | $24,462.46 | $24,462.46 | new aux antenna needed for change over | N/A | N/A |
Sweep test of existing antenna | $6,730.00 | $23,100.00 | tx line sweep | N/A | N/A |
Elbow complex, single channel, at antenna input, per 6 1/8. feedline (if needed) | $12,300.00 | $12,000.00 | elbow complex for new side mount aux antenna | N/A | N/A |
Side mount brackets for high power antennas (if not included in antenna base cost) | $23,150.00 | $22,000.00 | side mount brackets | N/A | N/A |
Pattern scatter analysis for side mount high/med power antennas (if not included in antenna base cost) | $5,260.00 | $8,000.00 | needed for pattern scatter analysis | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $0.00 | $0.00 | N/A | $0.00 | N/A |
Total for all systems | $1,830,617.95 | $1,385,342.95 | N/A | $0.00 | N/A |
Primary Transmission Line | $0.00 | $0.00 | $0.00 | ||
Auxiliary Transmission Line | $0.00 | $0.00 | $0.00 |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $666,300.00 | $245,100.00 | N/A | $0.00 | N/A |
Total for all systems | $1,830,617.95 | $1,385,342.95 | N/A | $0.00 | N/A |
Primary Tower NTOWER | $666,300.00 | $245,100.00 | $0.00 | ||
Minor tower reinforcement/modifications | $158,000.00 | $11,000.00 | N/A | N/A | N/A |
Tower mapping for an undocumented/poorly documented tower and preparation of documentation necessary for tower load study | $26,300.00 | $23,100.00 | N/A | N/A | N/A |
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) | $421,000.00 | $150,000.00 | N/A | N/A | N/A |
Tower Helicopter Lift | $50,000.00 | $50,000.00 | N/A | N/A | N/A |
Tower maintinance | $11,000.00 | $11,000.00 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $177,805.00 | $120,050.00 | N/A | $0.00 | N/A |
Total for all systems | $1,830,617.95 | $1,385,342.95 | N/A | $0.00 | N/A |
Outside Professional Services | $177,805.00 | $120,050.00 | $0.00 | ||
Project management of the transition | $18,960.00 | $25,000.00 | pm provided by gatesair | N/A | N/A |
Prepare and or review reimbursement form | $2,630.00 | $2,500.00 | N/A | N/A | N/A |
Address transition timing and coordination issues w/ other stations and wireless | $2,630.00 | $2,500.00 | N/A | N/A | N/A |
Perform engineering study for new channel assignment and antenna development | $7,360.00 | $7,000.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $3,155.00 | $3,000.00 | N/A | N/A | N/A |
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, Construction Permit Application | $2,105.00 | $4,000.00 | study done by hammet and edison | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,580.00 | $1,500.00 | N/A | N/A | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $5,260.00 | $5,000.00 | N/A | N/A | N/A |
Attorney Fees - Aux Antenna, prepare and File Form 2100 Construction Permit or License Application | $4,210.00 | $4,000.00 | N/A | N/A | N/A |
Comprehensive coverage verification via field study, if needed | $84,200.00 | $20,000.00 | N/A | N/A | N/A |
RF Exposure Measurements | $21,050.00 | $21,000.00 | RF studies | N/A | N/A |
Additional Field Engineering Service, 3 Days | $1,000.00 | $1,000.00 | RF engineer | N/A | N/A |
transmission line sweep | $21,300.00 | $21,300.00 | N/A | N/A | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $2,365.00 | $2,250.00 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $122,614.00 | $122,564.00 | N/A | $0.00 | N/A |
Total for all systems | $1,830,617.95 | $1,385,342.95 | N/A | $0.00 | N/A |
Other Expenses | $122,614.00 | $122,564.00 | $0.00 | ||
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $325.00 | N/A | N/A | N/A |
MVPD Notification of Channel Change | $6,000.00 | $6,000.00 | N/A | N/A | N/A |
FCC Filing Fees - Form 2100 minor change CP application | $1,110.00 | $1,070.00 | N/A | N/A | N/A |
Local Zoning | $3,500.00 | $3,500.00 | N/A | N/A | N/A |
Non-zoning permits | $2,000.00 | $2,000.00 | N/A | N/A | N/A |
Zoning and local permits | $2,000.00 | $2,000.00 | N/A | N/A | N/A |
Tower Lease Agreement modifications | $7,500.00 | $7,500.00 | N/A | N/A | N/A |
Develop and air announcement of upcoming channel change | $7,500.00 | $7,500.00 | N/A | N/A | N/A |
Disposal Costs (for equipment and other waste, net of any salvage value) | $66,669.00 | $66,669.00 | includes decommissioning of hazardous materials | N/A | N/A |
Equipment Delivery and Handling Charges | $25,000.00 | $25,000.00 | N/A | N/A | N/A |
Equipment Storage | $1,000.00 | $1,000.00 | N/A | N/A | N/A |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $1,830,617.95 | $1,385,342.95 | $0.00 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | No |
Construction of final facilities or all necessary modifications are complete. | No |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Phillip W. Meyer President & CEO 07/11/2017 |