Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
GRAHAM MEDIA GROUP, FLORIDA. INC. Doing Business As: GRAHAM MEDIA GROUP, FLORIDA. INC. |
James Lowery 4 BROADCAST PLACE JACKSONVILLE, FL 32207 United States |
+1 (904) 393-9871 | jlowery@wjxt.com | Corporation |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Robert Gehman ConsultingEngineer Kessler and Gehman Associates, Inc. |
Robert Gehman Kessler and Gehman Associates, Inc. 507 NW 60 Street, Suite D Gainesville, FL 32607 United States |
+1 (352) 332-3157 | bob@kesslerandgehman.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | No |
Briefly describe transition plan | Replace the transmitter, antenna and transmission line. No room on tower; therefore, interim facility must be at an alternate site. Map and analyze the complex 222-F candelabra tower; design, modify and strengthen tower to support post-transition load. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | Sigma CD3200P2 | |
Year | 2008 | |
Type | Inductive Output Tube | |
IOT Power Type | Two | |
Power Capacity | 42 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Manufacturer | ||
Model | DCX Paragon 2 | |
Transmitter Type | Inductive Output Tube | |
IOT Power Type | Two | |
Power capacity | 50 kW | |
Justification for New Transmitter | The manufacturer of the existing transmitter advises that the transmitter cannot be re-tuned to the assigned channel. See attachment. |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | Yes | |
Transformer (480V) | Yes | |
Power | 300 kVA | |
Rigid Conduit and Wiring | Yes | |
Size | 3 inches | |
Length | 100.0 feet | |
Other Electrical Service | Yes | |
Description | Additional electrical services required for constructing the new MSDC IOT while the existing IOT transmitter is in operation. | |
HVAC Service | Does the replacement transmitter require HVAC Service? | Yes |
Type | Cooling Only | |
Size | 10 tons | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | Yes |
Size | 400.0 square feet | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Name | Description |
---|---|
Standby Exciter and Switch |
Standby Exciter with Automatic Change Over Switch |
Additional Interior RF System |
Interior RF System Existing Transmitter to Interim Transmission line |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Interim |
Description of Use | N/A | |
Change Type | Purchase | |
Manufacturer | ||
Model | DCX Paragon 2 | |
Transmitter Type | Inductive Output Tube | |
IOT Power Type | Two | |
Power capacity | 50 kW | |
Justification for New Transmitter | The WJXT tower does not have sufficient space for an interim antenna; therefore, the interim facility must be located at an alternate site requiring a new interim transmitter capable of maintaining existing coverage. |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | Yes |
Switchgear (industrial 800 amp) | Yes | |
Transformer (480V) | Yes | |
Power | 300 kVA | |
Rigid Conduit and Wiring | Yes | |
Size | 2 inches | |
Length | 300.0 feet | |
Other Electrical Service | Yes | |
Description | Additional services required to install new transmitter at alternate site. | |
HVAC Service | Does the replacement transmitter require HVAC Service? | Yes |
Type | Cooling Only | |
Size | 10 tons | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | Yes |
Size | 400.0 square feet | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A | |
Inside RF System | Is an additional interior RF system required to support this interim transmitter? | Yes |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | Yes | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | Yes | |
Existing Antenna Manufacturer and Type | Class | Full Power |
Mounting | Top Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels | N/A | |
Design power capacity in use | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Other Antenna Type | N/A | |
ERP: | 976.0 kW | |
Manufacturer | ||
Model | TFU-30GTH 06 | |
Year | 2008 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | No | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | Yes | |
New Antenna Manufacturer and Types | Class | Full Power |
Mounting | Top Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Elliptical | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels/Bays | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Design power capacity in use | N/A | |
Other Antenna Type | N/A | |
ERP: | 587.0 kW | |
Manufacturer | ||
Model | TFU-24GTH/VP-R TC 06SP | |
Year | 2018 | |
Justification for New Antenna | The existing main antenna is a top-mount (candelabra) slot which cannot accommodate the post-auction channel. The proposed antenna is e-pol which is considered an upgrade with a 15% delta in costs according to Dielectric. The 399 is budgeted for h-pol. |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | No |
Type | ||
Number of channels supported | N/A | |
Frequencies of channels supported | N/A | |
Frequency | N/A | |
Do you need a combiner output splitter/switcher for dual feed lines? | N/A | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | Yes |
Broadband or Single Channel? | Single Channel | |
Feed Line Size | 6 1/8 inches inches | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | No |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Interim |
Description of Use | N/A | |
Change Type | Purchase New | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | No | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | Yes | |
New Antenna Manufacturer and Type | Class | Full Power |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels/Bays | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Design power capacity in use | N/A | |
Other Antenna Type | N/A | |
ERP: | 976.0 kW | |
Manufacturer | ||
Model | TFU-24GTH-R O6SP | |
Year | 2018 | |
Justification for New Antenna | An interim antenna is necessary to keep station on the air during primary antenna replacement and for the duration of the assigned phase. The interim facility will be located at an alternate site. |
Section | Question | Response |
---|---|---|
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | Yes |
Broadband or Single Channel? | S | |
Feed Line Size | 6 1/8 inches | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for an antenna? | Yes |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | Yes |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Rigid | |
Diameter | 6 1/8 inches | |
Other Diameter | N/A | |
Segment Length | 19 1/2 inches | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 1155 feet per run |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Type | Rigid | |
Diameter | 6 1/8 inches | |
Other Diameter | N/A | |
Segment Length | 20 inches | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 1155 feet per run | |
Justification for New Transmission Line | The existing primary transmission line is rigid with section lengths that are not recommended for the assigned channel. |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Interim |
Description of Use | N/A | |
Change Type | Purchase New | |
Type | Rigid | |
Diameter | 6 1/8 inches | |
Segment Length | 19 ½ ' | |
Other Segment Length | ||
Number of parallel runs | 1 | |
Length | 1050 feet per run | |
Justification for New Transmission Line | An interim transmission line is necessary to keep the pre-auction station on the air during the primary antenna replacement and for the duration of the assigned phase. The Interim facility must be at an alternate site since the WJXT tower is fully loaded. |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Is this tower consider Complex? | Candelabra | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | Yes | |
Others Types of Users | Yes | |
Is tower documented for structural analysis? | Yes | |
Is tower compliant with Rev G? | No | |
Existing Tower Structure Registration | Do you have a tower registration number? | No |
ASR Number | ||
Coordinates (NAD83) | Latitude (NAD83) | 30° 16' 25.0" N- |
Longitude (NAD83) | 081° 33' 12.0" W- | |
Overall Structure Height | 303.70 feet | |
Support Structure Height | 268.90 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 15.20 feet | |
Structure Type | TOWER - Free Standing or Guyed Structure | |
Tower Owner | First Coast Tower Group | |
Date Constructed | 01/01/1985 |
Facility ID | Call Sign | Service |
---|---|---|
65046 | WTLV | DTV |
11893 | WJXX | DTV |
Users |
---|
Two-way users |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | Study needed for tower with candelabra |
Tower Reinforcements | Please select whether tower reinforcements are needed: | Serious Reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | Candelabra |
Helicopter Services Required | Are helicopter services required? | Yes |
Name | Description |
---|---|
Foundation Expansion |
Geotechnical findings indicate existing foundation loading design is not adequate to support the post-transition loads. |
Existing Tower |
ASR is 1017604. The tower owner name was flagged by this application when it pre-filled so we had to manually enter. FAA & ASR required as a result of changing the top-mount antenna. |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 1500 | |
Explanation | It will be necessary to schedule and coordinate multiple vendors, complete progress reports, and update Schedule 399. Station does not have available personnel or personnel trained in project management for such complex projects. | |
Outside RF consulting Engineering Services | Perform engineering study for new channel assignment and antenna development | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
Do you have Distributed Transmission System engineering services? | N/A | |
Critical Facility | N/A | |
Terrain-Shielded Facility | N/A | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
NEPA Section 106 environmental review | Yes | |
Environmental Assessment | Yes | |
ASR Modification | Yes | |
FAA Consultation (including preparation of FAA Form 7460) | Yes | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Address transition timing and coordination issues w/ other stations and wireless providers | Yes | |
RF Field Engineering Services | Comprehensive coverage verification via field study | Yes |
RF exposure measurements | Yes | |
Additional Field Engineering Service | Yes | |
Number of Days | 45 | |
Justification | It will be necessary to survey the site, plan the equipment, develop specifications for purchasing, and oversee multiple vendor RF projects. Station does not have available personnel or personnel trained in such services. |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Facility Expenses | Name | N/A |
Other Distributed Transmission System Expenses Not listed | N/A | |
Name | N/A | |
Is Notification of a Medical Facility required as a result of DTV broadcasting? | Yes | |
Permit and Filing Costs | Local Zoning | No |
Non-zoning permits | Yes | |
BLM or NFS Coordination | No | |
FCC Construction Permit Minor Change | Yes | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | Yes | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | Yes | |
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? | Yes | |
Does this relocation require MVPD Notification of a Channel Change? | Yes |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $2,664,700.00 | $3,513,640.00 | N/A | $0.00 | N/A |
Total for all systems | $6,558,270.00 | $7,237,535.00 | N/A | $0.00 | N/A |
Interim Transmitter DCX Paragon 2 | $1,332,100.00 | $1,752,470.00 | $0.00 | ||
Two IOT system (50 kW) | $954,000.00 | $1,388,470.00 | Comark price list for a two-tube MSDC IOT | N/A | N/A |
Service entrance 3 phase/800 amp/208 volt | $14,400.00 | $13,700.00 | N/A | N/A | N/A |
UHF inside RF system including switching | $147,500.00 | $140,000.00 | N/A | N/A | N/A |
10 Ton system | $38,900.00 | $37,000.00 | N/A | N/A | N/A |
Switchgear - industrial 800 amp | $38,200.00 | $36,300.00 | N/A | N/A | N/A |
Transformer 3 phase/480v - 300 KVA | $36,800.00 | $35,000.00 | N/A | N/A | N/A |
Other -- Building Addition Size: 400.0 | $85,000.00 | $85,000.00 | N/A | N/A | N/A |
2" Rigid Conduit and Wiring (Cost per foot) | $7,800.00 | $7,500.00 | N/A | N/A | N/A |
Other Electrical Service: Additional services required to install new transmitter at alternate site. | $9,500.00 | $9,500.00 | N/A | N/A | N/A |
Primary Transmitter DCX Paragon 2 | $1,332,600.00 | $1,761,170.00 | $0.00 | ||
Transformer 3 phase/480v - 300 KVA | $36,800.00 | $35,000.00 | N/A | N/A | N/A |
3" Rigid Conduit and Wiring (Cost per foot) | $5,200.00 | $4,900.00 | N/A | N/A | N/A |
Switchgear - industrial 800 amp | $38,200.00 | $36,300.00 | N/A | N/A | N/A |
Other -- Building Addition Size: 400.0 | $85,000.00 | $85,000.00 | N/A | N/A | N/A |
10 Ton system | $38,900.00 | $37,000.00 | N/A | N/A | N/A |
Standby Exciter and Switch | $25,000.00 | $25,000.00 | N/A | N/A | N/A |
Additional Interior RF System | $140,000.00 | $140,000.00 | N/A | N/A | N/A |
Two IOT system (50 kW) | $954,000.00 | $1,388,470.00 | Comark price list for a two-tube MSDC IOT | N/A | N/A |
Other Electrical Service: Additional electrical services required for constructing the new MSDC IOT while the existing IOT transmitter is in operation. | $9,500.00 | $9,500.00 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $590,970.00 | $538,200.00 | N/A | $0.00 | N/A |
Total for all systems | $6,558,270.00 | $7,237,535.00 | N/A | $0.00 | N/A |
Interim Antenna TFU-24GTH-R O6SP | $282,440.00 | $280,100.00 | $0.00 | ||
Elbow complex, single channel, at antenna input, per 6 1/8. feedline (if needed) | $12,300.00 | $11,700.00 | N/A | N/A | N/A |
Sweep test of existing antenna | $6,730.00 | $6,400.00 | N/A | N/A | N/A |
Pattern scatter analysis for side mount high/med power antennas (if not included in antenna base cost) | $5,260.00 | $5,000.00 | N/A | N/A | N/A |
Side mount brackets for high power antennas (if not included in antenna base cost) | $23,150.00 | $22,000.00 | N/A | N/A | N/A |
UHF - High Power, Side Mount, basic slot antenna, 976 kW input, directional,, horizontally polarized | $235,000.00 | $235,000.00 | Required for interim operation at an alternate site while the main antenna and transmission line are installed on the candelabra at the licensed site. | N/A | N/A |
Primary Antenna TFU-24GTH/VP-R TC 06SP | $308,530.00 | $258,100.00 | $0.00 | ||
Sweep test of existing antenna | $6,730.00 | $6,400.00 | N/A | N/A | N/A |
Elbow complex, single channel, at antenna input, per 6 1/8. feedline (if needed) | $12,300.00 | $11,700.00 | N/A | N/A | N/A |
UHF - High Power Top Mount (200-1000 kW), One station antenna , elliptically or circularly polarized | $289,500.00 | $240,000.00 | Recognizing that e-pol is an upgrade, the station is budgeting for "h-pol only" which Dielectric said is a 15% delta. Therefore, the estimated cost for an h-pol antenna is only $240,000 instead of the estimated cost of $275,000 for an e-pol antenna (15%). | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $445,410.00 | $423,360.00 | N/A | $0.00 | N/A |
Total for all systems | $6,558,270.00 | $7,237,535.00 | N/A | $0.00 | N/A |
Interim Transmission Line | $212,100.00 | $201,600.00 | $0.00 | ||
Rigid Transmission Line - copper, 6 1/8" | $212,100.00 | $201,600.00 | N/A | N/A | N/A |
Primary Transmission Line | $233,310.00 | $221,760.00 | $0.00 | ||
Rigid Transmission Line - copper, 6 1/8" | $233,310.00 | $221,760.00 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $2,178,000.00 | $2,104,000.00 | N/A | $0.00 | N/A |
Total for all systems | $6,558,270.00 | $7,237,535.00 | N/A | $0.00 | N/A |
Primary Tower TOWER | $2,178,000.00 | $2,104,000.00 | $0.00 | ||
Structural engineering tower load study for a documented tower with candelabra | $20,000.00 | $19,000.00 | N/A | N/A | N/A |
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) | $421,000.00 | $400,000.00 | N/A | N/A | N/A |
Tower Helicopter Lift | $330,000.00 | $330,000.00 | Based on price information available from helicopter company's Website. | N/A | N/A |
Serious tower reinforcement/modifications | $1,052,000.00 | $1,000,000.00 | Fully loaded, complex candelabra tower going from 222-F to 222-G in a Class III designated area near the coast. | N/A | N/A |
Existing Tower | $5,000.00 | $5,000.00 | FAA 7460-1, FAA 7460-2 and FCC Form 854 applications required. | N/A | N/A |
Foundation Expansion | $350,000.00 | $350,000.00 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $484,000.00 | $463,750.00 | N/A | $0.00 | N/A |
Total for all systems | $6,558,270.00 | $7,237,535.00 | N/A | $0.00 | N/A |
Outside Professional Services | $484,000.00 | $463,750.00 | $0.00 | ||
Project management of the transition | $237,000.00 | $225,000.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,580.00 | $1,500.00 | N/A | N/A | N/A |
Address transition timing and coordination issues w/ other stations and wireless | $2,630.00 | $2,500.00 | N/A | N/A | N/A |
Additional Field Engineering Service, 45 Days | $90,000.00 | $90,000.00 | N/A | N/A | N/A |
Perform engineering study for new channel assignment and antenna development | $7,360.00 | $7,000.00 | N/A | N/A | N/A |
NEPA Section 106 environmental review, if needed | $6,310.00 | $6,000.00 | Soil issues from GEO report | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $3,155.00 | $3,000.00 | N/A | N/A | N/A |
Prepare and or review reimbursement form | $2,630.00 | $2,500.00 | N/A | N/A | N/A |
Prepare request for Special Temporary Authorization | $2,050.00 | $1,500.00 | N/A | N/A | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $5,260.00 | $5,000.00 | N/A | N/A | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $2,365.00 | $2,250.00 | N/A | N/A | N/A |
Attorney Fees - Prepare and File request for Special Temporary Authorization | $3,680.00 | $3,500.00 | N/A | N/A | N/A |
Environmental Assessment, if triggered by NEPA Section 106 review or for certain structures over 450 feet | $10,520.00 | $10,000.00 | Soil issues from GEO report | N/A | N/A |
ASR modification (prepare FCC Form 854) | $2,105.00 | $2,000.00 | N/A | N/A | N/A |
FAA consultant, including cost of preparing FAA Form 7460 (Notice of Proposed Construction), if needed for height increase | $2,105.00 | $2,000.00 | N/A | N/A | N/A |
Comprehensive coverage verification via field study, if needed | $84,200.00 | $80,000.00 | N/A | N/A | N/A |
RF Exposure Measurements | $21,050.00 | $20,000.00 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $195,190.00 | $194,585.00 | N/A | $0.00 | N/A |
Total for all systems | $6,558,270.00 | $7,237,535.00 | N/A | $0.00 | N/A |
Other Expenses | $195,190.00 | $194,585.00 | $0.00 | ||
MVPD Notification of Channel Change | $2,000.00 | $2,000.00 | N/A | N/A | N/A |
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $325.00 | N/A | N/A | N/A |
DTV Medical Facility Notification | $11,550.00 | $11,000.00 | N/A | N/A | N/A |
FCC Filing Fees - Form 2100 minor change CP application | $1,110.00 | $1,070.00 | N/A | N/A | N/A |
FCC Filing Fees - Special Temporary Authorization request | $195.00 | $190.00 | N/A | N/A | N/A |
Non-zoning permits | $10,000.00 | $10,000.00 | N/A | N/A | N/A |
Disposal Costs (for equipment and other waste, net of any salvage value) | $10,000.00 | $10,000.00 | N/A | N/A | N/A |
Equipment Delivery and Handling Charges | $50,000.00 | $50,000.00 | N/A | N/A | N/A |
Equipment Storage | $10,000.00 | $10,000.00 | N/A | N/A | N/A |
Develop and air announcement of upcoming channel change | $100,000.00 | $100,000.00 | N/A | N/A | N/A |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $6,558,270.00 | $7,237,535.00 | $0.00 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | No |
Construction of final facilities or all necessary modifications are complete. | No |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Heidi Schmid Whiting Secretary 07/11/2017 |