Go to the Federal Communications Commission homepage at www.fcc.gov

Licensing and Management System

Approved by OMB 3060-1240
September 2017
Go to the Federal Communications Commission homepage at www.fcc.gov

(REFERENCE COPY - Not for submission)Transition Plan Progress Report

File Number:
0000111297
Submit Date:
04/01/2020
Call Sign:
WTVU-CD
Facility ID:
617
FRN:
0004345773
State:
New York
City:
SYRACUSE
Service:
DCA
Purpose:
Transition Plan Progress Report
Status:
Received
Status Date:
04/01/2020
Filing Status:
Active


General Information

Section Question Response
Filing Information Filing Type 10 days after the construction of the post-auction facilities have been completed
Attachments Are attachments (other than associated schedules) being filed with this application? Yes

Applicant Information

Back to Top

Applicant Name, Type, and Contact Information

Applicant Address Phone Email Applicant Type

RENARD COMMUNICATIONS CORP.

Doing Business As: RENARD COMMUNICATIONS CORP.

Craig Fox

401 W. KIRKPATRICK ST.

SYRACUSE, NY 13204

United States

+1 (315) 468-0908 CRAIGF199@AOL.COM Corporation

Authorization Holder Name

Contact Representatives (2)

Back to Top
Contact Name Address Phone Email Contact Type

Craig Fox

Technical Director

Renard Communications Corp.

401 W. Kirkpatrick St.

Syracuse, NY 13204

United States

+1 (315) 468-0908 CraigF199@aol.com Technical Representative

James L. Oyster

Law Offices of James L. Oyster

108 Oyster Lane

Castleton, VA 22716

United States

+1 (540) 937-4800 oysterlaw@hotmail.com Legal Representative

Permits and Tower Studies

Back to Top
Section Question Response
Approval and Permits Does the Station require FAA approval (e.g., completion of FAA Form 7460-1 and a “No Hazard Determination”) in order to construct its post-auction facility? No
The Station has requested FAA approval for its post-auction facility.
The Station has received FAA approval for its post-auction facility.
Does the Station require Federal, State, and/or local permits, and/or a review of environmental impact, for its post-auction facility? No
Station has requested necessary Federal, State and/or local permits and/or review of environmental impact for its post-auction facility
Station has received necessary Federal, State, and/or local permits and/or review of environmental impact for its post-auction facility
Tower Studies Are radio frequency (RF) studies required in order for the Station to construct its post-auction facility? No
RF studies have been started
RF studies have been completed
Are structural tower studies required in order for the Station to construct its post-auction facility? Yes
Structural tower studies have been started Yes
Structural tower studies have been completed Yes

Station Equipment

Back to Top
Section Question Response
Station Equipment The Station has placed orders for the following equipment, if required:
Main Facility Antenna Yes
Main Facility Transmitter Yes
Main Facility Transmission line Yes
Main Facility Mask Filter and/or RF Combiner Yes
Auxiliary antenna and related equipment Not Applicable
Does the Station anticipate that it will receive all necessary equipment in time to meet the construction deadline for the Station’s main facility? Yes
Has Station received all required new broadcast equipment (antenna, transmitter, etc.) necessary to begin construction? Yes

Towers and Antenna

Back to Top
Section Question Response
Towers Construction and Antenna Installation Does the Station's post-auction facility require tower construction/modification work? Yes
Does construction of the Station’s post-auction facility require construction of a new tower or substantial modification of an existing tower? No
Has all necessary tower work been scheduled?
Has all necessary tower work been completed?
Does the Station anticipate that all tower work, including antenna installation, will be completed in time to meet its construction deadline? Yes
Auxiliary Antenna Does the Station require use of a new auxiliary antenna system? No
Has the Station started all outside tower work and made all necessary equipment upgrades to commence testing of its new auxiliary antenna system?
Has the Station completed all outside tower work and made all necessary equipment upgrades to commence testing of its new auxiliary antenna system?
Has the Station started testing on its new auxiliary antenna system?
Has the Station completed all testing on its new auxiliary antenna system such that it may now cease broadcasting on its pre-auction channel?
Post-auction Facility Has the Station completed all work, including construction, modification and/or installation, related to construction of its post-auction facility such that it is ready to begin testing on its post-auction facility? Yes
Has the Station completed all tower work?
Has the Station completed all in-building (equipment) work?
Does the Station have other issues that must be addressed before it can fully construct and/or operate its post-auction facility? No
Has the Station completed all construction work on its post-auction facility that is necessary to complete an application for a license to cover that facility? Yes
Pre-auction Channel Has the Station ceased broadcasting on its pre-auction channel? Yes

Certification

Back to Top
Section Question Response
General Certification Statements The Applicant waives any claim to the use of any particular frequency or of the electromagnetic spectrum as against the regulatory power of the United States because of the previous use of the same, whether by authorization or otherwise, and requests an Authorization in accordance with this application (See Section 304 of the Communications Act of 1934, as amended.).
The Applicant certifies that neither the Applicant nor any other party to the application is subject to a denial of Federal benefits pursuant to §5301 of the Anti-Drug Abuse Act of 1988, 21 U.S.C. §862, because of a conviction for possession or distribution of a controlled substance. This certification does not apply to applications filed in services exempted under §1.2002(c) of the rules, 47 CFR . See §1.2002(b) of the rules, 47 CFR §1.2002(b), for the definition of "party to the application" as used in this certification §1.2002(c). The Applicant certifies that all statements made in this application and in the exhibits, attachments, or documents incorporated by reference are material, are part of this application, and are true, complete, correct, and made in good faith.
Authorized Party to Sign

FAILURE TO SIGN THIS APPLICATION MAY RESULT IN DISMISSAL OF THE APPLICATION AND FORFEITURE OF ANY FEES PAID

Upon grant of this application, the Authorization Holder may be subject to certain construction or coverage requirements. Failure to meet the construction or coverage requirements will result in automatic cancellation of the Authorization. Consult appropriate FCC regulations to determine the construction or coverage requirements that apply to the type of Authorization requested in this application.

WILLFUL FALSE STATEMENTS MADE ON THIS FORM OR ANY ATTACHMENTS ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. Code, Title 18, §1001) AND/OR REVOCATION OF ANY STATION AUTHORIZATION (U.S. Code, Title 47, §312(a)(1)), AND/OR FORFEITURE (U.S. Code, Title 47, §503).

I certify that this application includes all required and relevant attachments. Yes
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

Craig Fox

President


04/01/2020

Attachments

Back to Top
File Name Uploaded By Attachment Type Description
WTVU-CD_10_DayPostTransitionStatement.pdf Applicant All Purpose Transition Statement